Lodi Unified School District                                            Lodi Unified School District
          George Washington Elementary School                                     George Washington Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                       Project Cost Summary (2016$) - George Washington Elementary School     Project Cost Summary (2016$) - George Washington Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          12 Safety, Security & Campus Control             $           1,911,000 $                 2,542,000  Total Construction/Project Cost (2016$)  $           7,984,000  $10,609,000
            12a  Remaining asbestos removal             46,151 sf  $                 4.00 $            185,000
            12b Safety improvements to and/or new parent/bus drop-off areas and parking
            12b.1 New Parking Lot              48,225 sf  $               16.00 $            386,000 Reconfig. Pkg. @ 50%  The following items are excluded from this budget:
            12b.3 Entry Plaza                     2,850 sf  $               26.00  Utility hook-up fees & City connection fees.
            12b.11 New concrete walkways                7,500 sf  $               15.00 $            113,000  Offsite work and traffic signals.
            12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $              40,000  Land acquisition costs.
            12e Safety locks at classroom doors                     35 ea  $             449.00 $              16,000  Hazardous material surveys, abatement, and disposal.
            12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $              32,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                1,405 lf  $             252.00 $            354,000
            12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $              27,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System             46,151 sf  $                 5.40 $            249,000
            12i.2 Emergency Lighting             46,151 sf  $                 1.40 $              65,000
            12j New public address/emergency communication
            systems                            46,151 sf  $                 7.60 $            351,000
            12k Intrusion alarms               46,151 sf  $                 1.80 $              83,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $                       -  $                             -
            14b Learning Courts
            14b.2 New Learning Court             20,400 sf  $               17.25
           15 Exterior Play Spaces, Playfields & Hardcourts  $                       -  $                             -
            15a Kindergarten Play Yard
            15a.1 New Rubberized Surface Play Area                1,200 sf  $               20.00
            15a.3 Shade Structure                 1,200 sf  $               90.00
            15b PE Play Yard & Hardcourts
            15a.1 New Rubberized Surface Play Area                5,000 sf  $               20.00
            15b.4 Shade Structure                 2,400 sf  $               90.00
            15b.6 New Hardcourts               18,850 sf  $               11.00
            15b.7 Slurry Coat & Stripe Existing Hardcourts             76,900 sf  $                 3.00
            15b.8 Basketball Court/Sports Equipment                        1 ls  $       25,333.33
            15c Playfields
            15c.1 Repair Playfields           138,600 sf  $                 3.00
           16 Next Generation Classroom Flexibility (Furniture)  $                       -  $                             -
            16a Flexible furniture (Per Classroom, Direct Cost)                     19 ea  $       15,000.00
           17 Technology Infrastructure                    $                 32,000 $                      32,000
             17c MDF and IDF data rooms with environmental control
            (direct cost only)                            1 ea  $       32,000.00 $              32,000



         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  627
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   651   652   653   654   655   656   657   658   659   660   661