Page 657 - Facilities Master Plan 2016
P. 657
Lodi Unified School District Lodi Unified School District
Westwood Elementary School Westwood Elementary School
Facilities Master Plan - Total Program Cost Facilities Master Plan - Total Program Cost
Opinion of Probable Cost 19-Apr-16 Opinion of Probable Cost 19-Apr-16
Project Cost Summary (2016$) - Westwood Elementary School Project Cost Summary (2016$) - Westwood Elementary School
Construction Costs Total Project Construction Costs Total Project
Item Quantity Unit Unit Cost Subtotal Total Cost 25% (x 1.33) Item Quantity Unit Unit Cost Subtotal Total Cost 25% (x 1.33)
4b New Construction - Classrooms
01 Modernize & Reconfigure Aging Classrooms $ - $ - 4b.2 Relocate Portable Classrooms 2 ea $ 25,000.00
1b Replacement or repair of walls 4b.3 Demolish Existing Buildings 7,680 sf $ 22.00
1b.1 Replace walls 1,920 sf $ 39.50
1b.2 Repair walls 12,300 sf $ 12.60 4b.4 New Elementary Classroom Building (1-story) 4,800 sf $ 404.00
1c Replacement or repair of windows 4b.10 Sitework & Site Improvements 4,800 sf $ 38.00
1c.2 Repair windows 14,220 sf $ 3.60
1d Replacement or repair of doors (other than safety locks
@ classroom doors) 05 Maker Spaces & Science Labs $ - $ -
1d.2 Repair doors & hardware 14,220 sf $ 4.50 5a ES Science / Creativity Labs
1e Replacement or repair of floors 5a.6 New ES Science / Creativity Labs Building 3,500 sf $ 440.00
1e.1 Replace floors 1,920 sf $ 14.40 5a.7 Sitework & Site Improvements 3,500 sf $ 38.00
1e.2 Repair floors 12,300 sf $ 10.80
1f Replacement or repair of ceilings
1f.1 Replace ceilings 1,920 sf $ 27.00 06 Electives $ - $ -
1f.2 Repair ceilings 12,300 sf $ 8.10 Not included in this Facilities Needs Assessment
1g Patch & Paint Interior/Exterior
1g.1 Patch & paint interior 14,220 sf $ 3.10
1g.2 Patch & paint exterior 14,220 sf $ 4.50 07 Performing Arts Improvements $ - $ -
1o Replace Existing Roofing 32,699 sf $ 20.93 7a Music Lab
1p Repair Existing Covered Walkways / Hallways 2,260 sf $ 13.00 7a.4 New Music Lab 1,750 sf $ 449.00
7a.5 Sitework & Site Improvements 1,750 sf $ 38.00
02 Existing Building Systems & Toilets $ - $ -
2a HVAC system upgrades 14,220 sf $ 29.00 08 Multi-Purpose Room / Food Service Improvements & Student Dining $ - $ -
8a Elementary/Middle School multipurpose rooms
2b Lighting upgrades - new interior lighting & controls 14,220 sf $ 15.00 8a.2 Modernize Multipurpose Room 4,660 sf $ 99.00
2c Electrical upgrades 8c Food service areas
2c.1 Upgrade electrical wiring & increase electrical 8c.2 Modernize Food Service 1,000 sf $ 175.00
outlets 14,220 sf $ 9.00 8c.6 New Trash Enclosure 1 ea $ 45,000.00
2d Plumbing system upgrades 14,220 sf $ 11.00
2e Replace aging plumbing, upgrade and/or expand
restroom facilities 09 Physical Education Improvements $ - $ -
2e.1 Modernize Existing Restroom 1,160 sf $ 83.00 9c PE/Fitness Labs
2f Energy-efficient building systems and controls (EMS 9c.4 New PE/Fitness Labs 2,400 sf $ 404.00
system, per sf of Bldg) 14,220 sf $ 7.20
9c.5 Sitework & Site Improvements 2,400 sf $ 38.00
03 Site Utilities $ - $ - 10 Administration & Staff Support $ - $ -
(For entire campus and site) 10a Expanded, reorganized or relocated administration
3a Updated gas service lines 566,280 sf $ 0.13 spaces
3b Updated sewer service lines 566,280 sf $ 0.21 10a.2 Modernize Administration 2,200 sf $ 118.00
3c Updated water service lines 566,280 sf $ 0.27 10b Staff Collaboration/Work Rooms
3d Updated electrical mains and distribution 566,280 sf $ 0.54 10b.2 Modernize Staff Collaboration/Work Rooms 1,459 sf $ 118.00
3f Electrical Capacity Upgrades 1 ls $ 115,000.00 10b.3 Reconfigure Staff Collaboration/Work Rooms 480 sf $ 235.00
04 Classrooms New Construction $ - $ -
11 Library & Student Support Services $ - $ -
11a Elementary School Library/Innovation Lab
4a New Construction - Pre-School, DK & Kindergarten
11a.4 Reconfigure Library/Innovation Lab Building 3,560 sf $ 244.00
11d Learning Center
4a.2 New Pre-School, DK & Kindergarten Building 2,970 sf $ 395.00
4a.4 Sitework & Site Improvements 2,970 sf $ 38.00 11d.4 Reconfigure Learning Center 1,700 sf $ 237.00
Prepared by: LPA, Inc. / Cumming Prepared by: LPA, Inc. / Cumming
6.3 APPENDIX Facilities Master Plan 628
DETAILED PRIORITIZED COST ESTIMATE Lodi Unified School District