Page 657 - Facilities Master Plan 2016
P. 657

Lodi Unified School District                                            Lodi Unified School District
          Westwood Elementary School                                              Westwood Elementary School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                     19-Apr-16  Opinion of Probable Cost                                    19-Apr-16
                         Project Cost Summary (2016$) - Westwood Elementary School               Project Cost Summary (2016$) - Westwood Elementary School
                                                       Construction Costs   Total Project                                      Construction Costs   Total Project
          Item                       Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                   4b New Construction - Classrooms
          01 Modernize & Reconfigure Aging Classrooms      $                       -  $                             -  4b.2 Relocate Portable Classrooms                        2 ea  $       25,000.00
            1b Replacement or repair of walls                                       4b.3 Demolish Existing Buildings                7,680 sf  $               22.00
            1b.1 Replace walls                     1,920 sf  $               39.50
            1b.2 Repair walls                   12,300 sf  $               12.60    4b.4 New Elementary Classroom Building (1-story)                4,800 sf  $             404.00
            1c Replacement or repair of windows                                     4b.10 Sitework & Site Improvements                4,800 sf  $               38.00
            1c.2 Repair windows                 14,220 sf  $                 3.60
            1d Replacement or repair of doors (other than safety locks
            @ classroom doors)                                                    05 Maker Spaces & Science Labs                  $                       -  $                             -
            1d.2 Repair doors & hardware             14,220 sf  $                 4.50  5a ES Science / Creativity Labs
            1e Replacement or repair of floors                                      5a.6 New ES Science / Creativity Labs Building                 3,500 sf  $             440.00
            1e.1 Replace floors                    1,920 sf  $               14.40  5a.7 Sitework & Site Improvements                3,500 sf  $               38.00
            1e.2 Repair floors                  12,300 sf  $               10.80
            1f Replacement or repair of ceilings
            1f.1 Replace ceilings                  1,920 sf  $               27.00  06 Electives                                  $                       -  $                             -
            1f.2 Repair ceilings                12,300 sf  $                 8.10  Not included in this Facilities Needs Assessment
            1g Patch & Paint Interior/Exterior
            1g.1 Patch & paint interior             14,220 sf  $                 3.10
            1g.2 Patch & paint exterior             14,220 sf  $                 4.50  07 Performing Arts Improvements            $                       -  $                             -
            1o Replace Existing Roofing             32,699 sf  $               20.93  7a Music Lab
            1p Repair Existing Covered Walkways / Hallways                2,260 sf  $               13.00  7a.4 New Music Lab                1,750 sf  $             449.00
                                                                                    7a.5 Sitework & Site Improvements                1,750 sf  $               38.00
          02 Existing Building Systems & Toilets           $                       -  $                             -
            2a HVAC system upgrades             14,220 sf  $               29.00  08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -
                                                                                   8a Elementary/Middle School multipurpose rooms
            2b Lighting upgrades - new interior lighting & controls             14,220 sf  $               15.00  8a.2 Modernize Multipurpose Room                4,660 sf  $               99.00
            2c Electrical upgrades                                                 8c Food service areas
            2c.1 Upgrade electrical wiring & increase electrical                    8c.2 Modernize Food Service                1,000 sf  $             175.00
            outlets                             14,220 sf  $                 9.00   8c.6 New Trash Enclosure                        1 ea  $       45,000.00
            2d Plumbing system upgrades             14,220 sf  $               11.00
            2e Replace aging plumbing, upgrade and/or expand
            restroom facilities                                                   09 Physical Education Improvements              $                       -  $                             -
            2e.1 Modernize Existing Restroom                1,160 sf  $               83.00  9c PE/Fitness Labs
            2f Energy-efficient building systems and controls (EMS                  9c.4 New PE/Fitness Labs                2,400 sf  $             404.00
            system, per sf of Bldg)             14,220 sf  $                 7.20
                                                                                    9c.5 Sitework & Site Improvements                2,400 sf  $               38.00
          03 Site Utilities                                $                       -  $                             -  10 Administration & Staff Support  $                       -  $                             -
            (For entire campus and site)                                           10a Expanded, reorganized or relocated administration
            3a Updated gas service lines           566,280 sf  $                 0.13  spaces
            3b Updated sewer service lines           566,280 sf  $                 0.21  10a.2 Modernize Administration                2,200 sf  $             118.00
            3c Updated water service lines           566,280 sf  $                 0.27  10b Staff Collaboration/Work Rooms
            3d Updated electrical mains and distribution           566,280 sf  $                 0.54  10b.2 Modernize Staff Collaboration/Work Rooms                1,459 sf  $             118.00
            3f Electrical Capacity Upgrades                        1 ls  $     115,000.00  10b.3 Reconfigure Staff Collaboration/Work Rooms                   480 sf  $             235.00
          04 Classrooms New Construction                   $                       -  $                             -
                                                                                  11 Library & Student Support Services           $                       -  $                             -
                                                                                   11a Elementary School Library/Innovation Lab
            4a New Construction - Pre-School, DK & Kindergarten
                                                                                    11a.4 Reconfigure Library/Innovation Lab Building                3,560 sf  $             244.00
                                                                                   11d Learning Center
            4a.2 New Pre-School, DK & Kindergarten Building                2,970 sf  $             395.00
            4a.4 Sitework & Site Improvements                2,970 sf  $               38.00  11d.4 Reconfigure Learning Center                1,700 sf  $             237.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.3       APPENDIX                                                                                                    Facilities Master Plan  628
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District