Page 661 - Facilities Master Plan 2016
P. 661

Lodi Unified School District                                            Lodi Unified School District
          Delta Sierra Middle School                                              Delta Sierra Middle School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                   19-Apr-16
                          Project Cost Summary (2016$) - Delta Sierra Middle School              Project Cost Summary (2016$) - Delta Sierra Middle School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
          01 Modernize & Reconfigure Aging Classrooms      $                       -  $                             -  05 Maker Spaces & Science Labs  $                       -  $                             -
            1b Replacement or repair of walls                                      5b MS / HS Science Labs
            1b.2 Repair walls                     9,040 sf  $               12.60   5b.3 Modernize  MS / HS Science Labs Building                 8,982 sf  $             132.00
            1c Replacement or repair of windows
            1c.2 Repair windows                   9,040 sf  $                 3.60
            1d Replacement or repair of doors (other than safety locks            06 Electives                                    $                       -  $                             -
            @ classroom doors)                                                     6a MS/HS Electives
            1d.2 Repair doors & hardware                9,040 sf  $                 4.50  6a.4 ModernizeMS/HS Electives Building                 6,222 sf  $             119.00
            1e Replacement or repair of floors
            1e.2 Repair floors                    9,040 sf  $               10.80
            1f Replacement or repair of ceilings                                  07 Performing Arts Improvements                 $                       -  $                             -
            1f.2 Repair ceilings                  9,040 sf  $                 8.10  7a Music Lab
            1g Patch & Paint Interior/Exterior                                      8a.2 Modernize Music Lab                1,728 sf  $             135.00
            1g.1 Patch & paint interior                9,040 sf  $                 3.10
                                                                                  08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -
          02 Existing Building Systems & Toilets           $                       -  $                             -  8a Elementary/Middle School multipurpose rooms
            2a HVAC system upgrades                9,040 sf  $               29.00  8a.2 Modernize Multipurpose Room                7,775 sf  $               99.00
                                                                                   8c Food service areas
            2b Lighting upgrades - new interior lighting & controls                9,040 sf  $               15.00  8c.2 Modernize Food Service                1,560 sf  $             175.00
            2c Electrical upgrades                                                  8c.6 New Trash Enclosure                        1 ea  $       45,000.00
            2c.1 Upgrade electrical wiring & increase electrical
            outlets                               9,040 sf  $                 9.00
            2d Plumbing system upgrades                9,040 sf  $               11.00  09 Physical Education Improvements        $           5,352,000 $                 7,118,000
            2e Replace aging plumbing, upgrade and/or expand                       9a New Gym and Lobby/Concessions                              P2
            restroom facilities                                                     9a.4 New Gymnasium                 10,010 sf  $             409.00 $         4,094,000
            2e.1 Modernize Existing Restroom                1,790 sf  $               83.00
            2f Energy-efficient building systems and controls (EMS                  9a.5 Sitework & Site Improvements             10,010 sf  $               38.00 $            380,000
            system, per sf of Bldg)                9,040 sf  $                 7.20  9b Changing/Locker Rooms
                                                                                    9b.4 New Changing/Locker Rooms                1,595 sf  $             512.00 $            817,000
                                                                                    9b.5 Sitework & Site Improvements                1,595 sf  $               38.00 $              61,000
                                                                                   9c PE/Fitness Labs
          03 Site Utilities                                $                       -  $                             -
            (For entire campus and site)                                            9c.4 New PE/Fitness Labs                1,760 sf  $             404.00
            3a Updated gas service lines           585,011 sf  $                 0.12  9c.5 Sitework & Site Improvements                1,760 sf  $               38.00
            3b Updated sewer service lines           585,011 sf  $                 0.25  9d MS / HS Weight Room
            3c Updated water service lines           585,011 sf  $                 0.32  9d.4 New Weight Room                1,760 sf  $             404.00
            3d Updated electrical mains and distribution           585,011 sf  $                 0.63  9d.5 Sitework & Site Improvements                1,760 sf  $               38.00
            3f Electrical Capacity Upgrades                        1 ls  $     161,000.00
                                                                                  10 Administration & Staff Support               $                       -  $                             -
                                                                                   10a Expanded, reorganized or relocated administration
          04 Classrooms New Construction                   $           2,368,000 $                 3,149,000  spaces
            4b New Construction - Classrooms                   (4) CR    P2         10a.3 Reconfigure Administration                2,618 sf  $             235.00
            4b.1 Remove Portable Classrooms                        4 ea  $       11,000.00 $              44,000
            4b.3 Demolish Existing Buildings  sf  $               22.00 $                     -  10b Staff Collaboration/Work Rooms
                                                                                    10b.3 Reconfigure Staff Collaboration/Work Rooms                1,305 sf  $             235.00
            4b.6 New Middle School Classroom Building (1-story)                4,224 sf  $             404.00 $         1,706,000
            4b.10 Sitework & Site Improvements                4,224 sf  $               38.00 $            161,000
            4d Student Collaboration Lab                                          11 Library & Student Support Services           $                       -  $                             -
            4d.1 New Student Collaboration Lab, 1- Story                1,056 sf  $             395.00 $            417,000  11b Middle School/High School Library/Innovation Lab
            4d.2 Sitework & Site Improvements                1,056 sf  $               38.00 $              40,000  11b.3 Modernize Library/Innovation Lab                   900 sf  $             122.00
                                                                                    11b.4 Reconfigure Library/Innovation Lab                4,500 sf  $             244.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.3       APPENDIX                                                                                                    Facilities Master Plan  632
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   656   657   658   659   660   661   662   663   664   665   666