Page 669 - Facilities Master Plan 2016
P. 669

Lodi Unified School District                                            Lodi Unified School District
          Morada Middle School                                                    Morada Middle School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                           Project Cost Summary (2016$) - Morada Middle School                     Project Cost Summary (2016$) - Morada Middle School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                   15c Playfields
          10 Administration & Staff Support                $                       -  $                             -  15c.1 Repair Playfields           228,600 sf  $                 3.00
            10a Expanded, reorganized or relocated administration                  15h DG Track                           1,315 lf  $               97.00
            spaces
            10a.3 Reconfigure Administration                4,320 sf  $             235.00
            10b Staff Collaboration/Work Rooms                                    16 Next Generation Classroom Flexibility (Furniture)  $                       -  $                             -
            10b.3 Reconfigure Staff Collaboration/Work Rooms                1,440 sf  $             235.00  16a Flexible furniture (Per Classroom, Direct Cost)                     15 ea  $       15,000.00
          11 Library & Student Support Services            $                       -  $                             -  17 Technology Infrastructure  $                 32,000 $                      32,000
            11b Middle School/High School Library/Innovation Lab                    17c MDF and IDF data rooms with environmental control
            11b.2 New Library/Innovation Lab                5,852 sf  $             438.48  2-story  (direct cost only)                         1 ea  $       32,000.00 $              32,000
            11b.5 Sitework & Site Improvements                2,926 sf  $               38.00
            11d Learning Center
            11d.4 Reconfigure Learning Center                2,080 sf  $             237.00  Total Construction/Project Cost (2016$)  $         12,815,000  $17,033,000
          12 Safety, Security & Campus Control             $           2,521,000 $                 3,353,000  The following items are excluded from this budget:
            12a  Remaining asbestos removal             38,396 sf  $                 4.00 $            154,000  Utility hook-up fees & City connection fees.
            12b Safety improvements to and/or new parent/bus drop-off areas and parking  Offsite work and traffic signals.
            12b.1 New Parking Lot              91,510 sf  $               16.00 $         1,464,000  Land acquisition costs.
            12b.3 Entry Plaza                     2,125 sf  $               26.00  Hazardous material surveys, abatement, and disposal.
            12d Exterior lighting to ensure student safety                        1 ls  $       20,000.00 $              20,000  Escalation (Costs are in 2016$ calculated to the end of the year).
            12e Safety locks at classroom doors                     40 ea  $             449.00 $              18,000
            12f Signage for emergency response and wayfinding                        1 ls  $       16,000.00 $              16,000
            12g Marquee Sign                              1 ea  $       10,000.00 $              10,000
            12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                   755 lf  $             252.00 $            190,000
            12h.3 Rolling Decorative Metal Gate                        1 ea  $       27,000.00 $              27,000
            12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System             38,396 sf  $                 5.40 $            207,000
            12i.2 Emergency Lighting             38,396 sf  $                 1.40 $              54,000
            12j New public address/emergency communication
            systems                            38,396 sf  $                 7.60 $            292,000
            12k Intrusion alarms               38,396 sf  $                 1.80 $              69,000
          13 District Support Facilities                   $                       -  $                             -
            Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads         $                       -  $                             -
            14a Main Student Quad
            14a.2 New Main Student Quad             19,950 sf  $               17.25
            14b Learning Courts
            14b.2 New Learning Court                7,000 sf  $               20.70
           15 Exterior Play Spaces, Playfields & Hardcourts  $                       -  $                             -
            15b PE Play Yard & Hardcourts
            15b.4 Shade Structure                 2,400 sf  $               90.00
            15b.5 Resurface & Repair Hardcourts             24,000 sf  $                 5.00
            15b.6 New Hardcourts               24,000 sf  $               11.00
            15b.8 Basketball Court/Sports Equipment                        1 ls  $       12,666.67

         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  640
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District