Page 670 - Facilities Master Plan 2016
P. 670

Lodi Unified School District                                            Lodi Unified School District
          Bear Creek High School                                                  Bear Creek High School
          Facilities Master Plan - Total Program Cost                             Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16   Opinion of Probable Cost                                    19-Apr-16
                           Project Cost Summary (2016$) - Bear Creek High School                  Project Cost Summary (2016$) - Bear Creek High School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item     Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
                                                                                   4d Student Collaboration Lab
          01 Modernize & Reconfigure Aging Classrooms      $                       -  $                             -  4d.1 New Student Collaboration Lab, 2- Story                   838 sf  $             426.60 $            357,000
            1b Replacement or repair of walls                                       4d.2 New Student Collaboration Lab, 1- Story                2,400 sf  $             395.00
            1b.2 Repair walls                  51,195 sf  $               12.60     4d.3 Sitework & Site Improvements                   419 sf  $               38.00 $              16,000
            1c Replacement or repair of windows
            1c.2 Repair windows                51,195 sf  $                 3.60
            1d Replacement or repair of doors (other than safety locks            05 Maker Spaces & Science Labs                  $           4,482,000 $                 5,961,000
            @ classroom doors)                                                     5b MS / HS Science Labs                            (4) SCI    P2
            1d.2 Repair doors & hardware             51,195 sf  $                 4.50  5b.1 New MS/HS  Science Labs Building                 9,576 sf  $             449.00 $         4,300,000
            1e Replacement or repair of floors                                      5b.2 Sitework & Site Improvements                4,788 sf  $               38.00 $            182,000
            1e.2 Repair floors                 51,195 sf  $               10.80     5b.3 Modernize MS / HS Science Labs Building              17,160 sf  $             132.00
            1f Replacement or repair of ceilings
            1f.2 Repair ceilings               51,195 sf  $                 8.10
            1g Patch & Paint Interior/Exterior                                    06 Electives                                    $                       -  $                             -
            1g.1 Patch & paint interior             51,195 sf  $                 3.10  6a MS/HS Electives
            1g.2 Patch & paint exterior             51,195 sf  $                 4.50  6a.4 ModernizeMS/HS Electives Building              29,995 sf  $             119.00
            1o Replace Existing Roofing           191,155 sf  $               14.65  6a.5 Reconfigure MS/HS Electives Building                 3,905 sf  $             237.00
            1p Repair Existing Covered Walkways / Hallways             28,875 sf  $               13.00  6a.6 New MS/HS Electives Building              14,388 sf  $             413.00
                                                                                    6a.7 Sitework & Site Improvements                7,194 sf  $               38.00
          02 Existing Building Systems & Toilets           $                       -  $                             -
            2a HVAC system upgrades             51,195 sf  $               29.00  07 Performing Arts Improvements                 $                       -  $                             -
                                                                                   7a Music Lab
            2b Lighting upgrades - new interior lighting & controls             51,195 sf  $               15.00  7a.4 New Music Lab                9,469 sf  $             449.00
            2c Electrical upgrades                                                  7a.5 Sitework & Site Improvements                9,469 sf  $               38.00
            2c.1 Upgrade electrical wiring & increase electrical                   7b Music/Drama/Dance and Support Spaces
            outlets                            51,195 sf  $                 9.00    7b.7 New Theatre support space                2,500 sf  $             428.00
            2d Plumbing system upgrades             51,195 sf  $               11.00  7b.8 Sitework & Site Improvements                2,500 sf  $               38.00
            2e Replace aging plumbing, upgrade and/or expand
            restroom facilities
            2e.1 Modernize Existing Restroom                8,330 sf  $               83.00
            2f Energy-efficient building systems and controls (EMS                08 Multi-Purpose Room / Food Service Improvements & Student Dining  $                       -  $                             -
            system, per sf of Bldg)             51,195 sf  $                 7.20  8b High School Cafeteria
                                                                                    8b.2 Modernize High School Cafeteria                7,100 sf  $             151.00
                                                                                   8c Food service areas
          03 Site Utilities                                $                       -  $                             -  8c.2 Modernize Food Service                3,925 sf  $             175.00
            (For entire campus and site)                                            8c.6 New Trash Enclosure                        1 ea  $       45,000.00
            3a Updated gas service lines        2,133,569 sf  $                 0.03
            3b Updated sewer service lines        2,133,569 sf  $                 0.05
            3c Updated water service lines        2,133,569 sf  $                 0.07  09 Physical Education Improvements        $                       -  $                             -
            3d Updated electrical mains and distribution        2,133,569 sf  $                 0.13  9a New Gym and Lobby/Concessions
            3f Electrical Capacity Upgrades                        1 ls  $     230,000.00  9a.2 Modernize Gymnasium             12,500 sf  $             123.00
                                                                                   9b Changing/Locker Rooms
                                                                                    9b.2 Modernize Changing/Locker Rooms             10,360 sf  $             154.00
          04 Classrooms New Construction                   $           6,448,000 $                 8,576,000
            4b New Construction - Classrooms                   (10) CR   P2
            4b.1 Remove Portable Classrooms                        9 ea  $       11,000.00 $              99,000  10 Administration & Staff Support  $                       -  $                             -
                                                                                   10a Expanded, reorganized or relocated administration
                                                                                   spaces
            4b.8 New High School Classroom Building (1-story)             20,256 sf  $             404.00
                                                                                    10a.2 Modernize Administration                5,130 sf  $             118.00
            4b.9 New High school Classroom Building (2-story)             12,768 sf  $             449.00 $         5,733,000  10b Staff Collaboration/Work Rooms
            4b.10 Sitework & Site Improvements                6,384 sf  $               38.00 $            243,000  10b.2 Modernize Staff Collaboration/Work Rooms                1,920 sf  $             118.00
         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming
         6.3       APPENDIX                                                                                                    Facilities Master Plan  641
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District