Page 667 - Facilities Master Plan 2016
P. 667

Lodi Unified School District                                           Lodi Unified School District
          Millswood Middle School                                                Millswood Middle School
          Facilities Master Plan - Total Program Cost                            Facilities Master Plan - Total Program Cost
          Opinion of Probable Cost                                    19-Apr-16  Opinion of Probable Cost                                     19-Apr-16
                          Project Cost Summary (2016$) - Millswood Middle School                  Project Cost Summary (2016$) - Millswood Middle School
                                                       Construction Costs   Total Project                                     Construction Costs   Total Project
          Item                      Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)  Item    Quantity  Unit  Unit Cost  Subtotal  Total  Cost 25% (x 1.33)
           9d MS / HS Weight Room
            9d.4 New Weight Room                  1,760 sf  $             404.00  17 Technology Infrastructure                    $                         -  $                             -
            9d.5 Sitework & Site Improvements                1,760 sf  $               38.00  Not included in this Facilities Needs Assessment
          10 Administration & Staff Support               $                         -  $                             -  Total Construction/Project Cost (2016$)  $             8,060,000  $10,719,000
           Not included in this Facilities Needs Assessment
                                                                                 The following items are excluded from this budget:
          11 Library & Student Support Services           $                         -  $                             -  Utility hook-up fees & City connection fees.
           11d Learning Center                                                    Offsite work and traffic signals.
            11d.4 Reconfigure Learning Center                2,248 sf  $             237.00  Land acquisition costs.
                                                                                  Hazardous material surveys, abatement, and disposal.
                                                                                  Escalation (Costs are in 2016$ calculated to the end of the year).
          12 Safety, Security & Campus Control            $                351,000 $                    467,000
           12b Safety improvements to and/or new parent/bus drop-off areas and parking
            12b.5 New Drop-off Area                9,800 sf  $               18.00 $             176,000
            12b.10 Slurry Coat & Stripe Existing Paving                8,500 sf  $                 2.00 $               17,000
            12b.11 New concrete walkways                1,800 sf  $               15.00 $               27,000
           12d Exterior lighting to ensure student safety                        1 ls  $       40,000.00 $               40,000
           12e Safety locks at classroom doors                     55 ea  $             449.00 $               25,000
           12f Signage for emergency response and wayfinding                        1 ls  $       32,000.00 $               32,000
           12g Marquee Sign                               1 ea  $       10,000.00 $               10,000
           12h Fencing with controlled campus entrances
            12h.2 Decorative Metal Fencing & Gates                     80 lf  $             252.00 $               20,000
           12i Fire safety equipment, fire alarms and emergency lighting
            12i.1 Fire Alarm System                2,248 sf  $                 5.40
            12i.2 Emergency Lighting                2,248 sf  $                 1.40
           12j New public address/emergency communication
           systems                                2,248 sf  $                 7.60
           12k Intrusion alarms                   2,248 sf  $                 1.80 $                 4,000
          13 District Support Facilities                  $                         -  $                             -
           Not included in this Facilities Needs Assessment
          14 Outdoor Learning Environments & Quads        $                         -  $                             -
           14b Learning Courts
            14b.2 New Learning Court                2,275 sf  $               23.00
          15 Exterior Play Spaces, Playfields & Hardcourts  $                         -  $                             -
           15b PE Play Yard & Hardcourts
            15b.4 Shade Structure                 2,400 sf  $               90.00
            15b.7 Slurry Coat & Stripe Existing Hardcourts             42,500 sf  $                 3.00
           15c Playfields
            15c.1 Repair Playfields           278,250 sf  $                 3.00
           15h DG Track                           1,315 lf  $               97.00
          16 Next Generation Classroom Flexibility (Furniture)  $                         -  $                             -
           16a Flexible furniture (Per Classroom, Direct Cost)                     25 ea  $       15,000.00


         Prepared by: LPA, Inc. / Cumming                                        Prepared by: LPA, Inc. / Cumming


         6.3       APPENDIX                                                                                                    Facilities Master Plan  638
                   DETAILED PRIORITIZED COST ESTIMATE                                                                      Lodi Unified School District
   662   663   664   665   666   667   668   669   670   671   672