                       INSTALLATION AND STARTUP


                       Chapter 2 Recommended Installation Sequence Checklist


                       Main


                          Become Familiar with Site

                            Building dimensions:   Location of:         Determine proper location:   Required Material:
                            •  Backroom dimension   •  Main water feed   •  Air Drops         •  Anticipate runs and material
                                                                                                required to complete install
                            •  Bay area dimension   •  Main Electrical feed   •  Wall Penetrations   (i.e. salt for softener,
                                                                        •  E-Stops              hydraulic hose assemblies)

                                                                                                       Chapter and/or
                            Item                 Installation Task                  Chapter Name
                                                                                                       Page Number(s)
                             1   DETERMINE EQUIPMENT LOCATIONS
                             1.a    Mount MCC and SCC Controller
                             1.b    Mount Chemical Pumps
                              1.c    Position RO Unit and Tank
                             1.d    Mount Dryer Panel
                             1.e    Mount HMI (Human Machine Interface): E-1063 or E-1063
                              1.f    Air compressor
                                   OPTIONAL ITEMS
                             1.g    Position Pumping Station
                             1.h    Reclaim modifications to Pumping station (if applicable)
                             2   MEET WITH ELECTRICIAN
                             2.a    Coordinate E-Stop Locations
                             2.b    Electricians install conduits and wires
                             3    ERECT FRESSSTYLER® FRAMEWORK
                             4    RAISE CARRIAGE ONTO RAILS
                             5    ERECT DRYER FRAME
                             6    INSTALL BOOM MOUNT TO WALL
                             7    INSTALL BOOM
                             8    OPTIONAL ITEMS
                             9   MEET WITH PLUMBER
                             9.a    Plan System Component drain system
                                     Including Air-Dump on compressor
                             9.b    Plumber installs hard plumbing
                            10   PLACE FLOOR ITEMS IN PROPER BAY LOCATION
                             10.a    Install Entrance Photo Eye
                             10.b    Install Point of Entry System / POS in store
                             10.c    Install Wait-Go / Navigational Signs
                             10.d    Install Rocker Blaster / Undercarriage Wash
                             10.e    Install Treadle and Bug Spray Option (if applicable)






















                        1MANUL220           Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (248) 349-7010 * Fax (248) 380-9681      2-1