Page 22 - FreesStyler® Installation and Startup
P. 22
®
INSTALLATION AND STARTUP
Chapter 2 Recommended Installation Sequence Checklist
Main
Chapter and/or
Item Installation Task Chapter Name Page Number(s)
ELECTRICIAN MOVES INSTALLATION TO BAY AREA
11 Electrical terminations made at MCC and SCC
12 Electrical terminations from Chemical Pumps to SCC
13 Electrical terminations made at Pumping Station (Optional)
14 Electrical terminations made at RO Unit
15 Electrical terminations made at Dryer Panel
16 Electrical terminations made at Dryer
17 Electrical terminations made at HMI
18 Electrical terminations made to Treadle
29 Electrical terminations made at Photo Eyes
20 Electrical terminations made at Entry Station / POS
21 Electrical terminations made at Navigational Signs
22 Electrical terminations made at ALL E-Stops
INSTALL SOFT PLUMBING
23 Install soft plumbing to Pumping Station (Optional)
24 Install soft plumbing to Chemical Pumps
25 Install soft plumbing to Carriage
26 Install soft plumbing to RO Unit
27 Install soft plumbing to Rocker Blaster / Undercarriage
PREP COMPONENTS
28 Enterlink™ / Hamilton Setups P.O.S.
29 Dryer adjustments
30 Prep Water Softener
31 Prep RO Unit
Optional Items to be Installed at any time
Chapter and/or
Item Installation Task Chapter Name
Page number(s)
Reclaim
Undercarriage, Undercarriage with Rust Inhibitor, Bug
Spray Aplicator, Triple Foam, Drying Agent, CTA, Wheel
Blaster, RO, Dually Treadle
When Installation Finalized
Chapter and/or
Item Installation Task Chapter Name
Page number(s)
32 Complete the Start Up Procedure
33 Dryer Adjustments
34 Run Test Vehicles with customer
35 Customer Training on Operation