Page 22 - FreesStyler® Installation and Startup
P. 22

®
            INSTALLATION AND STARTUP


            Chapter 2 Recommended Installation Sequence Checklist


            Main

                                                                                            Chapter and/or
                 Item               Installation Task                 Chapter Name         Page Number(s)
                ELECTRICIAN MOVES INSTALLATION TO BAY AREA
                 11     Electrical terminations made at MCC and SCC
                 12     Electrical terminations from Chemical Pumps to SCC
                 13     Electrical terminations made at Pumping Station (Optional)
                 14     Electrical terminations made at RO Unit
                 15     Electrical terminations made at Dryer Panel
                 16     Electrical terminations made at Dryer
                 17     Electrical terminations made at HMI
                 18     Electrical terminations made to Treadle
                 29     Electrical terminations made at Photo Eyes
                 20     Electrical terminations made at Entry Station / POS
                 21     Electrical terminations made at Navigational Signs
                 22     Electrical terminations made at ALL E-Stops
                INSTALL SOFT PLUMBING
                 23     Install soft plumbing to Pumping Station (Optional)
                 24     Install soft plumbing to Chemical Pumps
                 25     Install soft plumbing to Carriage
                 26     Install soft plumbing to RO Unit
                 27     Install soft plumbing to Rocker Blaster / Undercarriage
                     PREP COMPONENTS
                 28     Enterlink™ / Hamilton Setups P.O.S.
                 29     Dryer adjustments
                 30     Prep Water Softener
                 31     Prep RO Unit

            Optional Items to be Installed at any time

                                                                                        Chapter and/or
                Item              Installation Task               Chapter Name
                                                                                        Page number(s)
                        Reclaim
                        Undercarriage, Undercarriage with Rust Inhibitor, Bug
                       Spray Aplicator, Triple Foam, Drying Agent, CTA, Wheel
                       Blaster, RO, Dually Treadle

            When Installation Finalized

                                                                                        Chapter and/or
                Item              Installation Task               Chapter Name
                                                                                        Page number(s)
                 32     Complete the Start Up Procedure
                 33     Dryer Adjustments
                 34     Run Test Vehicles with customer
                 35     Customer Training on Operation