Page 87 - FreesStyler® Installation and Startup
P. 87
®
INSTALLATION AND STARTUP
Chapter 4 Frame and Carriage Assembly
Optional On-Board Wheel Cleaner
Connections of Utilities and Internal Plumbing
Note: If the multi-stage centrifigul pump was supplied by Belanger, follow the steps below. If it was
field supplied, the utility supply lines MUST match your pumps output requirements.
1) Locate the supplied 1-1/4” hose.
2) Feed the hose through the boom. It is important that the 1-1/4” hose be run on the entrance side of the boom. This
assures the greatest bending radius during operation. Be sure there is enough slack at the bend of the boom and
on the Freestyler’s side as stated earlier in this section.
3) Attach the 1-1/4” hose to the Internal manifolds barbed hose fitting.
4) Secure the 1-1/4” hose in place with a worm gear clamp.
5) Verify that the 1-1/4” hose has enough slack to allow for smooth operation.
6) Wire-tie the 1-1/4” hose securely within the boom as stated earlier in this section.
7) From the supply side of the boom measure the remaining length of hose required to reach the field supplied line*
from the utility boom.
If the supplied 1-1/4” water-hose is not long enough (33ft. supplied by Belanger) and it is necessary to purchase a
longer hose from the field, the specifications are as follows:
500PSI 8” Bend Radius (minimum)
Additional hose can be purchased by the foot from Belanger as part #1HOSE820
8) Cut 1 1/4” hose to the measured length. DO NOT throw the remaining hose away.
9) Attach and Secure the 1-1/4” hose to the field supplied line.
Note: The difference in set-up from location to location requires that a link or field supplied line be
the responsibility of the owner. 1-1/2” Type M Copper is the suggested material of the field
supplied line.
Setting up the Pumping Station
1) Remove pumping station unit from the packing crate, and position into approximate location.
2) Verify that remaining 1-1/4” hose is enough to reach the field supplied line* from the pumps location.
3) Once it is in its permanent location, lag it to the floor.
4) Attach and Secure the remaining 1-1/4” hose between the 1-1/4” barb hose fitting on the pumping station to the
field supplied line*.
5) Attach and secure a 3/4” supply line to the barb hose fitting found below the tank on the inlet side of the solenoid
valve.
Type M Copper
1-1/4" (31.8 1-1/2" (38.1 2" (50.8
mm) mm) mm)
40 GPM 1.15/.079 0.51/.035 N/A
PSI per 10 foot of pipe/BAR per 3 meters of pipe
1MANUL220 Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (248) 349-7010 * Fax (248) 380-9681 4-45