Page 32 - Wave Wrap™
P. 32
WAVE WRAP™
Installation
Neo-Tex Cleaning Material
Upper Hub
1) Mount the two 6” diameter x 42-1/2” tall hubs so that they set on top
of the lower hubs by securing the “Spider” Clamps to the shafts and
securing the “Skins” to the Spiders as shown. Be sure that the open
ends of the “C” channels are facing upward (FIGURE 1).
2) Locate the 41” x 8” Neo-Tex pieces that are 1/4” thick (thicker Neo-
Tex material). Fold them in half and place one in the first, middle
and last slot of each skin of the hub, making sure they are pushed
all the way to the bottom (FIGURE 2).
3) Locate the 25” x 8” Neo-Tex pieces that are 1/8” thick (thinner Neo-
Tex material). Load two pieces onto each 8” clip to provide the fill
for this row. Place 12 of these assemblies into the previous slots
filled to continue stacking the upper hub.
4) Locate the 25” x 8” Neo-Tex pieces that are 1/4” thick (thicker Neo-
Tex material). Load one piece onto each 8” clip to provide the fill for
this row. Place 12 of these assemblies into the previous slots filled
to continue stacking the upper hub.
5) Locate the 28” x 8” Neo-Tex pieces that are 1/4" thick (thicker Neo-
Tex material). Load one piece onto each 8” clip to provide the fill for
this row. Place 12 of these assemblies into the previous slots filled
to continue stacking the upper hub.
6) Locate the 32” x 10” Neo-Tex pieces that are 1/4" thick (thicker
Neo-Tex material) Load one piece onto each 10” clip to provide the
fill for this row. Place 12 of these assemblies into the previous slots
filled to continue stacking the upper hub.
First, middle
and last slot
of a skin
FIGURE 2
Upper Hub
(Top view)
FIGURE 1
Top Row 32” x 10”
Insert into one 10” clip.
FIGURE 3
30 Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (248) 349-7010 * Fax (248) 380-9681 1MANUL864