1) Locate the following parts:
Item Qty Corner Clamp Pieces (2)
Dryer Leg Weldment 2
Corner Clamp Assembly 2
Black Plastic Caps 4
Lag Bolt 3 Zinc 5/8 x 6 8
2) Locate the skid that the head beam assembly shipped on. Clamp the head beam
assembly to the forks of the forklift and position it in its tunnel location.
3) Lift it until there is a 91” clearance from the bottom surface of the head beam to the floor.
4) Slide one of the clamp assemblies and one of the legs into place as shown below but do
not tighten the bolts until the height is set and the frame has been leveled. Be sure
the base of the legs face the entrance of the tunnel.
Before After
5) Secure the clamp and leg into place on the other side. Do not tighten the bolts until
the height is set and the frame has been leveled.