Page 37 - Airblade® Dryer - Mix and Match
P. 37

AIRBLADE® DRYER Mix and Match



                       Installation


                       4-Nozzle “Select” Frame Assembly: Floor Mounted

                          Tunnel Positioning

                              Note:  Drip space is the distance between the last Rinse Arch and the Dryer. Typically, the larger
                                     the drip space, the better the Dryer can perform.

                              1)  Once both legs have been attached to the head beam, space them  as  shown  in  the
                                 image below.













                                                        136”                       91”




                                          45”

                                                        Floor


                              Note:  45” dimension is taken from the outside of the driver side leg to the inside of the passenger
                                     side Guide Rail. Actual tunnel depth will vary according to available building space.



                              2)  Once the component is properly placed,  leveled in all directions and the legs are
                                 squared, you can tighten all of the fasteners and lag the frame to the floor.