Page 13 - Twin Wave Mitter™
P. 13

®
                       TWIN WAVE MITTER


                       Installation


                       Tunnel Placement

                       When placing a piece of equipment, tunnel depth will vary from site to site. Be sure to allow an adequate
                       operating envelope.

                          1)  Position the assembled unit in its permanent tunnel location.
                          2)  While placing a level on the vertical surface of one of the legs, place shims under the base
                              plate as needed to make the assembly level in both directions. Repeat this leveling process
                              on the other leg.
                              Note:  Shims not supplied by Belanger, Inc.

                          3)  Once the assembly is positioned correctly and level, lag it to the floor using the supplied lag
                              bolts.










                                                             DIRECTION
                                                                  of
                                                               TRAVEL

















                                                               Center
                                                                Line



                                        45”






                                          The 45” dimension is taken from the inside edge of the inside conveyor guide rail to the outside edge of the equipment leg.