Page 21 - Saber® Installation & Startup
P. 21

INSTALLATION & STARTUP

                      Chapter 2 Recommended Installation Sequence Checklist



                      Main

                          Become Familiar with Site

                           Building dimensions:   Location of:        Determine proper location:   Required Material:
                            ·  Backroom dimension   ·  Main water feed   ·  Air Drops      ·  Anticipate runs and material
                                                                                              required to complete install
                            ·  Bay area dimension   ·  Main Electrical feed   ·  Wall Penetrations   (i.e. salt for softener,
                                                                                              hydraulic hose assemblies)
                                                                      ·  E-Stops
                                                                                                  Chapter and/or
                           Item             Installation Task               Chapter Name          Page number(s)
                            1   DETERMINE EQUIPMENT LOCATIONS
                             1.a    Mount Electrical Panels       Electrical, & Support Documents   5 and 25
                             1.b    Mount SDM                     Pumping Station / Solution Delivery Module   7
                             1.c    Position Pumping Station      Pumping  Station  /  Solution  Delivery  Module   7
                             1.d    Position RO Unit & Tank       (SDM)                               12
                                                                  Spot Free Rinse (RO)
                             1.e    Mount Dryer Panel             Saber® Dryer                        16
                             1.f    Mount HMI Panel               Electrical                          5
                             1.g    Position Water Softener       Water Softener                      11
                             1.h    Air compressor                Refer to manufacturer instructions
                                  OPTIONAL ITEMS
                             1.i    Reclaim modifications to Pumping station – If applicable  Reclaim Water (option)   19
                            2   MEET WITH ELECTRICIAN             Trades                              4
                             2.a    Coordinate E-Stop Locations   Not supplied by Belanger, Inc.
                             2.b    Electricians install conduits and wires
                            3    ERECT Saber® FRAMEWORK           Frame and Carriage Assembly         6
                            4    RAISE CARRIAGE ONTO RAILS        Frame and Carriage Assembly         6
                            5    ERECT DRYER FRAME                Frame and Carriage Assembly         6
                            6    INSTALL WALL MOUNT               Frame and Carriage Assembly         6
                            7    INSTALL BOOM MOUNT TO WALL       Frame and Carriage Assembly         6
                            8    INSTALL WALL MANIFOLD            Frame and Carriage Assembly         6
                            9    INSTALL BOOM                     Frame and Carriage Assembly         6
                           10    INSTALL KNUCKLE & MANIFOLDS      Frame and Carriage Assembly         6
                           11    PENETRATE UTILITIES THROUGH WALL   Wall Manifold / Super Water Heater   8
                            11.a      Install “Thru wall plate kit” – if applicable                   8-5
                                 OPTIONAL ITEMS
                            11.b    Install Super Water Heater – if applicable                        8-6
                           12   MEET WITH PLUMBER                 Trades                              4
                            12.a    Plan System Component drain system
                                    Including Air-Dump on compressor                                  8-5
                            12.b    Plumber installs hard plumbing
                           13   PLACE FLOOR ITEMS IN PROPER BAY LOCATION
                            13.a    Install Entrance Photo Eye    Photo Eyes                          22
                            13.b    Install Point of Entry System / POS in store   Entry System       10
                            13.c    Install Wait-Go / Navigational Signs   Signage                    15
                            13.d    Install Rocker Blaster / Undercarriage Wash   Rocker Blaster / Undercarriage Wash    13
                           14   CRIMP & ASSEMBLE NECESSARY HOSE ASSEMBLIES  Getting Started           3