Chapter 2 Recommended Installation Sequence Checklist
Main
Chapter and/or
Item Installation Task Chapter Name Page number(s)
ELECTRICIAN MOVES INSTALLATION TO BAY AREA CRITICAL!
15 Electrical terminations made at MCC Electrical 5 and 25
16 Electrical terminations from SDM to MCC Pumping Station / Solution Delivery Module 7
17 Electrical terminations made at Pumping Station Pumping Station / Solution Delivery Module 7
18 Electrical terminations made at RO Unit Spot Free Rinse (RO) 12
19 Electrical terminations made at Dryer Panel
20 Electrical terminations made at Dryer
21 Electrical terminations made at HMI Electrical 5 and 25
22 Make connections to Motor Control Box Electrical 5 and 25
24 Electrical terminations made at Photo Eye Electrical 5 and 25
25 Electrical terminations made at Entry Station / POS Electrical 5 and 25
26 Electrical terminations made at Navigational Signs Electrical 7
27 Electrical terminations made at ALL E-Stops
28 Electrical terminations made at Super Heater – if applicable Wall Manifold and Super Heater 7
INSTALL SOFT PLUMBING
29 Install soft plumbing to Pumping Station Pumping Station / Solution Delivery Module 8
30 Install soft plumbing to SDM Pumping Station / Solution Delivery Module 8
31 Install soft plumbing to Wall Manifold Wall Manifold and Super Heater 12
32 Install soft plumbing to RO Unit Spot Free Rinse (RO) 11
33 Install soft plumbing to Water Softener Water Softener 16
34 Install soft plumbing to Dryer Dryer 13
35 Install soft plumbing to Rocker Blaster / Undercarriage Rocker Blaster / Undercarriage Wash 10
36 Install soft plumbing to Super Heater – if applicable Wall Manifold and Super Heater 7
PREP COMPONENTS
37 Enterlink™ / Hamilton Setups P.O.S. Entry System 16
38 Dryer adjustments Dryer 11
39 Prep Water Softener Water Softener 13
40 Prep RO Unit
41 Additional Chemical Option Additional Chemical Option 18
42 High Pressure Wax High Pressure Wax 5 and 25
Optional Items to be Installed at any time
Item Installation Task Chapter Name Chapter and/or
Page number(s)
Reclaim
When Installation Finalized
Item Installation Task Chapter Name Chapter and/or
Page number(s)
43 Complete the Start Up Procedure Initial Startup Procedure 24
44 Dryer Adjustments Saber® Dryer 16
45 Run Test Vehicles with customer Startup Procedure – Quick Reference 7