Page 18 - DuraFlo™ 18 GPM Pump Station
P. 18

DURAFLO™ 18 GPM PUMPING STATIONS


            Installation


            Initial Startup
                   1)  Verify the proper motor and pump rotation according to the decal on the plastic belt guard. See the image
                       below.


































                   2)  Refer to the Wanner™ Hydra-Cell section in this manual for the initial startup procedures for the pump.

                   3)  Verify that the water inlet valve flow rate is set correctly and does not exceed 100 psi.
                   4)  Verify that all hose fittings and clamps are tight.
                   5)  Flush out the component that is connected to the DuraFlo™ pumping station before installing any nozzles.
             Note:  Check the drive belt tension after the first 8 hours of service.  Refer to the Belt Tension chart in
                    this manual for the proper tension rating.