Page 20 - Rain Arch (all styles)
P. 20

RAIN ARCH MANUAL


             Installation


             Triple Manifold for Ceiling Mount

                 This configuration gives the ability to mount up to three Rain Arch manifolds from the ceiling anywhere
                 along the length of the tunnel.

                 The method used to hang the frame must be field determined and field supplied.













                1)  The Mounting Brackets are to be secured to the ceiling in the position shown below.



                                                                              Field Determined



                                                            36-3/4”      18-3/8”
                                     Tunnel Centerline
                                                                         18-3/8”




                                                    Overhead view of carwash tunnel

                2)  A method of securing the field supplied mounting system to the Rain Arch Mounting Plates
                    will need to adapt to the configuration shown below.
                                                         4-7/8”

                                                          2-3/8”





                                                                    4-3/4”

                                              Overhead view of Mounting Bracket
                3)  Bolt the three Rain Arch Manifolds to the weldment using the supplied
                    3/8-16 x 1” fasteners.
                Manifolds can be fed from either side. They should be fed from the
                Equipment Room side.




                                                                                      Securing the Manifolds