                       Installation


                       Installing Cleaning Material

                          Upper Hub: Neo-Tex®
                              Note:  The cleaning material for the upper hub comes in two thicknesses. 1/8” thick and 1/4”
                                     thick. Be sure to install the correct thickness in the correct location.
                              1)  Locate 12 of the 41” x 8” x 1/8” thick Neo-Tex® pieces and twelve 8” Wash Clips.
                              2)  Place the Wash Clips it in the center of the pack as shown below. Fold the Neo-Tex® pieces in half
                                 and slide the Wash Clips “C” Channels.


                                 Wash                                        Insert Wash        Fold Neo-Tex® in
                                  Clip                                       Clips into         half to slide into
                                            Neo-Tex®                         Neo-Tex®
                                                                             holes              “C” Channels


                              3)  Fill every third “C” Channel slot as shown below (12 pieces in all). Make sure the Packs are pushed
                                 all the way to the bottom of the hub.


                                     Hub Overhead View              Fill every third slot


                                                                                            12 (41” x 8”) Pieces of
                                                                                            Neo-Tex® Folded in half
                                                                                            12 Wash Clips










                              4)  Locate 24 of the 25” x 8” x 1/8” thick Neo-Tex® pieces and twelve 8” Wash Clips.
                              5)  Place the Wash Clips ends through the holes if both packs as shown below.


                                                         2 pieces of 25” x 8” x x1/8”
                                                         thick Neo-Tex® per slot


                              6)  Fill every third “C” Channel slot as shown below (12 pieces in all). Make sure the Packs are pushed
                                 down as far as possible. Be sure the flaps are in the direction as shown below.