Page 16 - UNIARCH
P. 16
UNIARCH
Installation
Tunnel Placement
When placing a piece of equipment, tunnel depth will vary from site to site. Be sure to allow an
adequate operating envelope
1) Once UNIARCH is fully assembled, stand it up in the appropriate location and lag the driver side leg
to the floor.
Direction
of
Travel
45”
Overhead View
Dimensions are taken from the outer equipment leg to the driver side edge of the inside guide rail
2) Confirm that the legs are evenly spaced at the top and bottom and the Arch is level in both
directions. Lag the other side to the floor.
Be sure legs are spaced the same at top and bottom
Be sure legs are spaced the same at top and bottom
Note: Make sure that the UNIARCH is level. Check that there is an equal measurement from the
driver’s side to the passenger’s side at both the top and bottom of the UNIARCH legs.
14 Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (810) 349-7010 * Fax (248) 380-9681 1MANUL795