Page 56 - 2016 Budget, Bond and Innovation Recommendations
P. 56

Transportation



                          Due to age, we recommend replacing the current electrical and HVAC
                          systems at the Smoky Hill Central Transportation Terminal, as they are
                          inefficient and do not function properly.

                          This structure was built in Cherry Creek at a time when fewer employees
                          occupied the central transportation facility. For safety and efficiency,
                          we recommend redesigning this building to accommodate the 180-200

                          employees that access the building each work day.


                          Cost:   $1,000,000