            Concrete Footings, Grade Beams and Stem Walls. Use the figures below for preliminary estimates.
            Concrete costs are based on a 2,000 PSI, 5.0 sack mix with 1" aggregate placed directly from the
            chute of a ready-mix truck. Figures in parentheses show the cubic yards of concrete per linear foot of
            foundation including 5 percent waste. Costs shown include concrete, 60 pounds of reinforcing per CY of
            concrete, and typical excavation using a 3/4 CY backhoe with excess backfill spread on site.

            Concrete footings and grade beams. Cast directly against the earth, including excavation, steel
            reinforcing and concrete but no forming or finishing. These costs assume the top of the foundation will
            be at finished grade. For scheduling purposes estimate that a crew of 3 can lay out, excavate, place
            and tie the reinforcing steel and place 13 CY of concrete in an 8-hour day. Add the cost of equipment
            rental. Use $900.00 as a minimum job charge.
              Using 2,000 PSI concrete, per CY               --@.000  CY    116.15         --    116.15
              Using reinforcing bars, per pound              --@.000   Lb     0.71         --       0.71
              Typical cost per CY                           B4@1.80   CY    159.58     72.40     231.98
              12" W x   6" D (0.019CY per LF)               B4@.034   LF      3.04       1.37       4.41
              12" W x   8" D (0.025CY per LF)               B4@.045   LF      4.01       1.81       5.82
              12" W x 10" D (0.032 CY per LF)               B4@.058   LF      5.10       2.33       7.43
              12" W x 12" D (0.039 CY per LF)               B4@.070   LF      6.24       2.82       9.06
              12" W x 18" D (0.058 CY per LF)               B4@.104   LF      9.29       4.18     13.48
              16" W x   8" D (0.035 CY per LF)              B4@.063   LF      5.63       2.53       8.16
              16" W x 10" D (0.043 CY per LF)               B4@.077   LF      6.89       3.10       9.99
              16" W x 12" D (0.052 CY per LF)               B4@.094   LF      8.31       3.78     12.09
              18" W x   8" D (0.037 CY per LF)              B4@.067   LF      5.92       2.70       8.61
              18" W x 10" D (0.049 CY per LF)               B4@.088   LF      7.86       3.54     11.40
              18" W x 24" D (0.117 CY per LF)               B4@.216   LF     18.89       8.69     27.58
              20" W x 12" D (0.065 CY per LF)               B4@.117   LF     10.40       4.71     15.11
              24" W x 12" D (0.078 CY per LF)               B4@.140   LF     12.42       5.63     18.05
              24" W x 24" D (0.156 CY per LF)               B4@.281   LF     24.85     11.30      36.15
              24" W x 30" D (0.195 CY per LF)               B4@.351   LF     31.31     14.12      45.43
              24" W x 36" D (0.234 CY per LF)               B4@.421   LF     37.47     16.93      54.40
              30" W x 36" D (0.292 CY per LF)               B4@.526   LF     46.66     21.16      67.82
              30" W x 42" D (0.341 CY per LF)               B4@.614   LF     54.54     24.70      79.24
              36" W x 48" D (0.467 CY per LF)               B4@.841   LF     74.54     33.83     108.37
            To estimate the cost of footing or grade beam sizes not shown, multiply the width in inches by the
            depth in inches and divide the result by 3700. This is the CY of concrete per LF of footing including 5
            percent waste. Multiply by the “Typical cost per CY” in the prior table to find the cost per LF.

            Continuous concrete footing with foundation stem wall. These figures assume the foundation stem
            wall projects 24" above the finished grade and extends into the soil 18" to the top of the footing. Costs
            shown include typical excavation using a 3/4 CY backhoe with excess backfill spread on site, forming
            both sides of the foundation wall and the footing, based on three uses of the forms and 2 #4 rebar. Use
            $1,200.00 as a minimum cost for this type work. Add the cost of equipment rental.
              Typical cost per CY                           B5@7.16   CY    183.82    285.40     469.22

            Concrete footing and stem wall for single-story structure.
              Typical single-story structure, footing 12" W x 8" D,
               wall 6" T x 42" D (.10 CY per LF)            B5@.716   LF     18.38     28.54      46.92


            Concrete footing and stem wall for two-story structure.
              Typical two-story structure, footing 18" W x 10" D,
               wall 8" T x 42" D (.14 CY per LF)            B5@1.00   LF     25.65     39.86      65.51


            Concrete footing and stem wall for three-story structure.
              Typical three-story structure, footing 24" W x 12" D,
               wall 10" T x 42" D (.19 CY per LF)           B5@1.36   LF     34.85     54.21      89.06