Concrete wall finish.
Cut back ties and patch B6@.011 SF 0.15 0.39 0.54
Remove fins B6@.008 LF 0.05 0.28 0.33
Grind smooth B6@.021 SF 0.10 0.74 0.84
Sack, burlap grout rub B6@.013 SF 0.06 0.46 0.52
Wire brush, green B6@.015 SF 0.05 0.53 0.58
Wash with acid and rinse B6@.004 SF 0.23 0.14 0.37
Break fins, patch voids, carborundum rub B6@.035 SF 0.07 1.24 1.31
Break fins, patch voids, burlap grout rub B6@.026 SF 0.07 0.92 0.99
Specialty finishes
Monolithic natural aggregate topping
3/16" B6@.020 SF 0.31 0.71 1.02
1/2" B6@.022 SF 0.35 0.78 1.13
Integral colors
Primary colors, based on 25 lb sack --@.000 Lb 6.36 -- 6.36
Blends, based on 25 lb sack --@.000 Lb 2.37 -- 2.37
Colored release agent --@.000 Lb 2.37 -- 2.37
Dry shake colored hardener --@.000 Lb 0.53 -- 0.53
Stamped finish (embossed concrete) of joints, if required
Diamond, square, octagonal patterns B6@.047 SF -- 1.66 1.66
Spanish paver pattern B6@.053 SF -- 1.88 1.88
Add for grouting B6@.023 SF 0.35 0.81 1.17
Concrete slab sawing, Subcontract. Typical rates quoted by concrete sawing subcontractors. Using
a gasoline powered saw. Costs per linear foot for cured concrete assuming a level surface with good
access and saw cut lines laid out and pre-marked by others. Costs include local travel time. Minimum
cost will be $250. Electric powered slab sawing will be approximately 40 percent higher for the same
depth.
Under 200' to Over
Depth Unit 200' 1000' 1000'
1" deep LF 0.75 0.66 0.55
1-1/2" deep LF 1.10 1.01 0.84
2" deep LF 1.45 1.28 1.10
2-1/2" deep LF 1.83 1.64 1.36
3" deep LF 2.20 1.91 1.64
3-1/2" deep LF 2.55 2.29 1.91
4" deep LF 2.91 2.55 2.20
5" deep LF 3.93 3.19 2.74
6" deep LF 4.39 3.85 3.29
7" deep LF 5.30 4.55 3.93
8" deep LF 6.02 5.29 4.55
9" deep LF 6.86 6.02 5.21
10" deep LF 7.76 6.86 5.94
11" deep LF 8.66 7.66 6.65
12" deep LF 9.59 8.50 7.40