Page 66 - 2018 National Home Improvement
P. 66

2018 National Home Improvement Estimator, All Rights Reserved                                    Page 49



            Concrete slabs, walks and driveways. Typical costs for reinforced concrete slabs-on-grade including
            fine grading, slab base, forms, vapor barrier, wire mesh, 3,000 PSI concrete, finishing and curing. For
            thickened edge slabs, add the area of the thickened edge. Use 500 square feet as the minimum job
            size.
              2" thick                                      B5@.067   SF      2.11       2.67       4.78
              3" thick                                      B5@.068   SF      2.48       2.71       5.19
              4" thick                                      B5@.069   SF      2.86       2.75       5.61
              5" thick                                      B5@.070   SF      3.23       2.79       6.02
              6" thick                                      B5@.071   SF      3.61       2.83       6.44

            Slab Base. Aggregate base for slabs. No waste included. Labor costs are for spreading aggregate from
            piles only. Add for fine grading, using hand tools.
            Crushed stone base 1.4 tons equal one cubic yard
              Using crushed stone, per CY                    --@.000  CY     38.58         --     38.58
              1" base ( .309 CY per CSF)                    BL@.001   SF      0.12       0.03       0.15
              2" base ( .617 CY per CSF)                    BL@.003   SF      0.24       0.10       0.34
              3" base ( .926 CY per CSF)                    BL@.004   SF      0.35       0.13       0.48
              4" base (1.23  CY per CSF)                    BL@.006   SF      0.47       0.20       0.67
              5" base (1.54  CY per CSF)                    BL@.007   SF      0.60       0.23       0.82
              6" base (1.85  CY per CSF)                    BL@.008   SF      0.72       0.26       0.98
            Sand fill base 1.40 tons equal one cubic yard
              Using sand, per CY                             --@.000  CY     17.98         --     17.98
              1" fill ( .309 CY per CSF)                    BL@.001   SF      0.05       0.03       0.08
              2" fill ( .617 CY per CSF)                    BL@.002   SF      0.11       0.07       0.18
              3" fill ( .926 CY per CSF)                    BL@.003   SF      0.16       0.10       0.26
              4" fill (1.23  CY per CSF)                    BL@.004   SF      0.22       0.13       0.35
              5" fill (1.54  CY per CSF)                    BL@.006   SF      0.27       0.20       0.47
              6" fill (1.85  CY per CSF)                    BL@.007   SF      0.33       0.23       0.56
              Add for fine grading for slab on grade        BL@.008   SF         --      0.26       0.26

            Concrete finishing.
            Slab finishes
              Broom finish                                  B6@.012   SF         --      0.43       0.43
              Float finish                                  B6@.010   SF         --      0.35       0.35
            Trowel finishing
              Steel, machine work                           B6@.015   SF         --      0.53       0.53
              Steel, hand work                              B6@.018   SF         --      0.64       0.64
            Finish treads and risers
              No abrasives, no plastering, per LF of tread  B6@.042   LF         --      1.49       1.49
              With abrasives, plastered, per LF of tread    B6@.063   LF      0.73       2.23       2.96
              Scoring concrete surface, hand work           B6@.005   LF         --      0.18       0.18
              Sweep, scrub and wash down                    B6@.006   SF      0.04       0.21       0.25
            Liquid curing and sealing compound, spray-on, acrylic concrete cure and seal,
              400 SF per gallon                             B6@.003   SF      0.21       0.11       0.32
            Exposed aggregate (washed, including finishing),
              no disposal of slurry                         B6@.017   SF      0.35       0.60       0.96
            Non-metallic color and concrete hardener, troweled on, 2 applications, red, gray or black,
                60 pounds per 100 SF                        B6@.021   SF      0.53       0.74       1.27
              100 pounds per 100 SF                         B6@.025   SF      0.87       0.89       1.75
   61   62   63   64   65   66   67   68   69   70   71