Page 262 - WU183.indd
P. 262
WORLD U18
6. MOI INTERNATIONAL SPORTS CENTRE, KASARANI – MAIN FIELD – CIVIL WORKS
WP ITEM N0. D113 NB/NB/1601 JOB NO. 10141K
Main Contractor: M/S Newtral Enterprises Limited
P O Box 590-00503
NAIROBI
A) Contract Data
i) Commencement Date - 2nd February 2017
ii) Contract period - 16 weeks
KYEB
-
7th June 2017
iii) Completion date
N/A
-
iv) Revised Completion Date
-
v)
Ksh. 44,650,140
Contract sum
vi) Revised Tender sum
N/A
-
vii) Amount Certifi ed to date
-
Kshs. 44,650,140.00
-
100%
viii) % Funds Certifi ed to date
-
ix) Contract Period
16 weeks
-
16 weeks
Elapsed contract Period
x)
100%
-
xi) % Work done
xii) Contract period elapsed
-
100%
B) Scope of Works
Grotto
KENYA YEARBO0K
i)
Wire brushing ,keying and bag washing of the wall
Steel framing of the grotto deck
ii)
iii) Chequered plate welded on the steel frame
iv) Two stair case to grotto done
EDITORIAL BOARD
v)
Steel stair done
vi) Deck riveting and stiff ening
vii) Final primer coating
viii) Scabbing of the concrete pavement
ix) Paving slabs: cleaning and replacing of the paving slab
C) Status of Works
General status is 100% complete as broken down below:
GROTTO
i) Wire brushing, keying and bag washing of the wall done
ii) Steel framing of the grotto deck done to 100%
iii) Chequered plate welded on the steel frame to 100%
iv) Two stair cases to grotto done
v) Steel stair done
vi) Paving slabs: cleaning and replacing of the paving slab
262 | ACTIVITIES AND OCCURENCES DURING WORLD U18 CHAMPIONSHIPS