                       6.  MOI INTERNATIONAL SPORTS CENTRE, KASARANI – MAIN FIELD – CIVIL WORKS
                           WP ITEM N0. D113 NB/NB/1601 JOB NO. 10141K


                           Main Contractor:         M/S Newtral Enterprises Limited
                                                                   P O Box 590-00503
                                                                   NAIROBI
                           A)  Contract Data

                          i)    Commencement Date           -     2nd  February 2017
                          ii)    Contract period           -      16 weeks
                  KYEB
                                                           -
                                                                  7th June 2017
                          iii)   Completion date
                                                                  N/A
                                                           -
                          iv)   Revised Completion Date
                                                           -
                          v)
                                                                  Ksh. 44,650,140
                               Contract sum
                          vi)   Revised Tender sum
                                                                  N/A

                                                           -
                          vii)   Amount Certifi ed to date
                                                           -
                                                                  Kshs. 44,650,140.00
                                                           -
                                                                  100%
                          viii)   % Funds Certifi ed to date

                                                           -
                          ix)   Contract Period
                                                                  16 weeks
                                                           -
                                                                  16 weeks
                               Elapsed contract Period
                          x)

                                                                   100%
                                                           -
                          xi)   % Work done
                          xii)   Contract period elapsed
                                                           -
                                                                  100%
                           B)    Scope of Works
                           Grotto
                     KENYA  YEARBO0K
                           i)
                               Wire brushing ,keying and bag washing  of the wall
                               Steel framing of the grotto deck
                           ii)
                           iii)   Chequered plate welded on the steel frame
                           iv)   Two stair case to grotto done
                      EDITORIAL BOARD
                           v)
                               Steel stair done
                           vi)   Deck riveting and stiff ening
                           vii)   Final primer coating
                           viii)   Scabbing of the concrete pavement
                           ix)  Paving slabs: cleaning and replacing of the paving slab
                           C)  Status of Works
                           General status is 100% complete as broken down below:
                           GROTTO
                           i)     Wire brushing, keying and bag washing  of the wall done
                           ii)    Steel framing of the grotto deck done to 100%
                           iii)   Chequered plate welded on the steel frame to 100%
                           iv)   Two stair cases to grotto done
                           v)    Steel stair done
                           vi)   Paving slabs: cleaning and replacing of the paving slab