Page 259 - WU183.indd
P. 259
IAAF W ORLD U18 REPORT
Water reticulation
i) Repair works on existing pipe work reticulation
ii) Replacement and reinstatement of pumpsets
Water irrigation system
i) Trenching, pipe laying and connections
ii) Testing, backfi lling and compaction
iii) Irrigation points and chamber construction
KYEB
C) Status of the Works
Overall status is 100% complete as broken down below:
i) Foundation Works and pump house
100%
100%
ii) Tank installation and pipe connections
100%
iii) Pump set supply and installation
100%
iii) Repair works on existing pipe work reticulation
100%
iv) Replacement of leaking sections and fi ttings
100%
v) Replacement and reinstatement of pump sets
100%
vi) Trenching, pipe laying and connections
vii) Testing, backfi lling and compaction
100%
100%
viii) Irrigation points and chamber construction
KENYA YEARBO0K
5. MOI INTERNATIONAL SPORTS CENTRE, KASARANI – WARM-UP FIELDS – CIVIL WORKS
WP ITEM N0. D113 NB/NB/1601 JOB NO. 10141J
M/S Resjos Enterprises Limited
Main Contractor:
EDITORIAL BOARD
P. O. Box 28689-00100
NAIROBI
A) Contract Data
i) Commencement Date - 2nd February 2017
ii) Contract period - 16 weeks
iii) Completion date - 2nd June 2017
iv) Revised Completion Date - N/A
v) Contract sum - Kshs. 118,286354.80
vi) Revised Tender sum - N/A
vii) Amount Certifi ed to date - Kshs. 118,286354.80
viii) % Funds Certifi ed to date - 100%
ix) Contract Period - 16 weeks
x) Elapsed contract Period - 16 weeks
xi) % Work done - 100%
xii) Contract period elapsed - 100%
ACTIVITIES AND OCCURENCES DURING WORLD U18 CHAMPIONSHIPS | 259