IAAF W ORLD U18 REPORT









                          Water reticulation

                          i)   Repair works on existing pipe work reticulation
                          ii)   Replacement and reinstatement of pumpsets
                          Water irrigation system


                          i)   Trenching, pipe laying and connections
                          ii)   Testing, backfi lling and compaction
                          iii)   Irrigation points and chamber construction

                   KYEB
                          C) Status of the Works

                          Overall status is 100% complete as broken down below:


                          i)   Foundation Works and pump house

                                                                                 100%



                                                                                 100%
                          ii)   Tank installation and pipe connections


                                                                                 100%
                          iii)   Pump set supply and installation
                                                                                 100%
                          iii)   Repair works on existing pipe work reticulation


                                                                                 100%
                          iv)   Replacement of leaking sections and fi ttings

                                                                                 100%
                          v)   Replacement and reinstatement of pump sets

                                                                                 100%
                          vi)   Trenching, pipe laying and connections



                          vii)  Testing, backfi lling and compaction
                                                                                 100%
                                                                                 100%

                          viii)  Irrigation points and chamber construction
                      KENYA  YEARBO0K
                       5.   MOI INTERNATIONAL SPORTS CENTRE, KASARANI – WARM-UP FIELDS – CIVIL WORKS

                           WP ITEM N0. D113 NB/NB/1601 JOB NO. 10141J
                                                    M/S Resjos Enterprises Limited

                          Main Contractor:
                       EDITORIAL BOARD

                                                    P. O. Box 28689-00100

                                                    NAIROBI


                          A)   Contract Data
                          i)   Commencement Date           -      2nd  February 2017
                          ii)   Contract period            -      16 weeks
                          iii)   Completion date           -      2nd  June 2017
                          iv)   Revised Completion Date    -      N/A
                          v)   Contract sum                -      Kshs. 118,286354.80
                          vi)   Revised Tender sum         -      N/A
                          vii)  Amount Certifi ed to date     -    Kshs. 118,286354.80
                          viii) % Funds Certifi ed to date    -    100%
                          ix)   Contract Period            -      16 weeks
                          x)   Elapsed contract Period     -      16 weeks
                          xi)   % Work done                -       100%
                          xii)   Contract period elapsed     -    100%