IAAF W ORLD U18 REPORT









                       B)  Scope of Works

                          i)   Rehabilitation of Changing Rooms
                          ii)   Tiling of Corridors and External Relaxing Areas (in Eurocon tiles)
                          iii)  Gypsum Ceiling Works in Offi  ces and Entry Porches
                          iv)  Concreting the fl oor areas below the terraces
                          v)   Paintworks and General Repair Works
                          vi)  Construction of Equipment Store
                       C) Status of the Works                     100% Complete.

                   KYEB
                          General status is 100% complete as broken down below:
                              Changing Rooms
                          a)
                              Tiling of Corridors
                                                                  100% Complete


                          b)

                                                                  100% complete
                          c)
                              Gypsum Ceiling Works
                          d)   Concrete Slab below Terraces
                                                                  100% Complete.

                              and Plastering of Walls

                              Paint Works and General Repairs
                          e)
                                                                  100% Complete
                          f)


                              Equipment Store
                                                                  100% complete
                       3.   MOI INTERNATIONAL SPORTS CENTRE, KASARANI
                           – BOREHOLE DRILLING AND EQUIPPING WORKS


                           WP ITEM N0. D113 NB/NB/1601 JOB NO. 10141E
                      KENYA  YEARBO0K
                          Main Contractor:
                                                    M/ S Pumpken Engineering Company
                                                    P.O Box 58835-00200
                                                    Nairobi
                       EDITORIAL BOARD
                          A) Contract Data
                                                                  Kshs. 20,608,708.00

                                                           -
                               Contract Sum
                          i)
                                                                  6th February 2017
                                                           -
                          ii)   Commencement Date
                          iii)   Completion Date                    -             7th June 2017
                          iv)   % Work done
                               Borehole Drilling           -      100%
                               Borehole Equipping          -      100%
                          v)   Amount certifi ed            -      Kshs 20,608,708.00
                          vi)   % of Amount Certifi ed      -      100%
                          vii)   Time Elapsed                     -   16 weeks
                          viii)  % of period lapsed        -       100%
                          B)   Scope of Works
                              Borehole Drilling
                          i)   Borehole, drilling casing and gravel pack installation
                          ii)   Well development and test pumping
                          iii)  Water testing, chemical analysis and well capping


                                                   ACTIVITIES AND OCCURENCES DURING WORLD U18 CHAMPIONSHIPS  | 255