                       Project Statuts Report For International Association Of Athletics Federations  IAAF  World
                       Under 18 Championships,  Nairobi 2017

                       Projects Status Report As At 12th January 2018
                   KYEB

                                           Local Organizing Committee, International Association of Athletics Federations
                       i) Client:
                                           (IAAF) World Under 18 Championship Nairobi 2017

                       ii)   Project Manager:  Works Secretary,Ministry of Transport, Infrastructure, Housing & Urban Development


                       1.   MOI INTERNATIONAL SPORTS CENTRE BUILDERS WORKS

                           WP ITEM N0. D113 NB/NB/1601 JOB NO. 10141A
                                                           M/ S Ocean Bays Investment & General Supplies

                          Main Contractor:

                                                           P O Box 43059-00100



                                                           Nairobi

                          Nominated Contractor:
                      KENYA  YEARBO0K
                                                           M/S Prowatt Enterprises Ltd




                                                           P O Box 873-00600
                                                           Nairobi
                          A) Contract Data
                       EDITORIAL BOARD
                               Contract Sum
                                                                  Kshs. 101,896,093.6

                          i)
                                                           -
                          ii)
                          iii)    Commencement Date        -      6th February 2017
                                                           -             7th June 2017
                               Completion Date
                          iv)    % Work done               -      100%
                          v)    Amount certifi ed           -      Kshs 101,896,093.6
                          vi)    % of Amount Certifi ed     -      100%
                          vii)   Time Elapsed                  -   16 weeks
                          viii)   % of period lapsed       -      100%
                          B)    Scope of Works
                          i)   Construction of New Photo Finish Structure.
                          ii)   Tiling of Corridors and External Relaxing Areas (in Eurocon tiles)
                          iii)   Gypsum Ceiling Works in Offi  ces and Entry Porches
                          iv)   Concreting the fl oor areas below the terraces
                          v)   Paintworks and General Repairs
                          vi)   Creation of new ablution facilities for Media Centre (extra works)