WORLD U18











                          Borehole Equipping

                          i)   Pump sizing, supply and installation
                          ii)   Trenching, pipe laying and connections
                          iii)  Cable supply, installation, connection and control equipment installation

                          C) Status of the Works

                          Overall status is 100% complete as broken down below:    100%

                  KYEB
                          i)   Borehole, drilling casing and gravel pack installation

                                                                                 100%
                          ii)   Well development and test pumping
                          iii)  Water testing, chemical analysis and well capping
                                                                                 100%


                          iv)  Pump sizing, supply and installation
                                                                                 100%

                                                                                 100%

                          v)   Trenching, pipe laying and connections
                          vi)  Cable supply, installation, connection and
                                                                                 100%
                             control equipment installation
                       4.  MOI INTERNATIONAL SPORTS CENTRE, KASARANI - HIGH AND LOW LEVEL WATER
                           TANKS AND WATER RETICULATION INSTALLATION WORKS

                           WP ITEM N0. D113 NB/NB/1601 JOB NO. 10141F
                          Main Contractor:
                                                    M/ S Walden East Africa Limited
                                                    P.O Box 8192-00200
                     KENYA  YEARBO0K
                                                    Nairobi
                          A)   Contract Data
                      EDITORIAL BOARD
                          i)   Contract Sum



                                                                          Kshs. 42,239,310.00
                                                                  -


                                                                          6th February 2017
                                                                  -
                          ii)   Commencement Date
                          iii)  Completion Date

                                                                  -             7th June 2017
                             High and low level water tanks
                            iv)  % Work done                      -       100%
                             Water reticulation                   -       100%
                             Water irrigation system              -       100%
                          v)   Amount certifi ed                   -       Kshs 42,239,310.00
                          vi)  % of Amount Certifi ed              -       100%
                          vii)  Time Elapsed                       -      16 weeks
                          viii)  % of period lapsed               -        100%
                          B) Scope of Works
                          High and low level water tanks
                          i)   Foundation Works and pump house
                          ii)   Tank installation and pipe connections
                          iii)  Pump set supply and installation