B) Scope of works
Upper warm area
i) Excavation of the top layer of grass
ii) Leveling and formation of the fi eld
iii) Top red soil supply and spread
iv) Manure mixed with red soil
v) Culvers for drainage supply and fi xing
vi) Grassing
KYEB
Lower warm area
i) Excavation of the top layer of grass
ii) Leveling and formation of the fi eld
iii) Top red roil supply and spread
iv) Carpet grass
v) Drainage line
vi) Grassing
C) Works progress
Upper warm area
General status is 100% complete as broken down below:
KENYA YEARBO0K
e following works have been done on upper warm –up area
i)
Excavation of the top layer of grass
ii)
iii) Leveling and formation of the fi eld
EDITORIAL BOARD
iv) Top red roil supplied and spread
v)
Manure mixed the red soil in progress –is now 100% complete
vi) Culverts for drainage supplied ready for fi xing (the existing drainage levels are maintained ).
vii) Grassing Culverts and construction of inspection chambers done to 100%.
Lower warm area
General status is 100% complete as broken down below:
i) Excavation of the top layer of grass
ii) Leveling and formation of the fi eld
iii) Top red roil supplied and spread
iv) Carpet grass done to 100% and watering done
v) Drainage line opened and repair done
vi) Grassing in progress to 100% complete