PHASE 2 – PRE - HANDOVER
Critical phase in any project for all parties
Proper planning for the move – in and induction of end users
Senior users training and induction by the main contractor as per commissioning
requirements
Proper training for the non – technical end users
Pre – handover triggers the assembly of guidelines for the building final handover
Pre – handover phase prompt building management with issues they need to
plan for to get the building up and running efficiently during and after the move
A simple non – technical end user guide should be assembled, over and above
compulsory technical guidance, using the pre handover pictures of building
controls with a few simple guidelines to explain key control and energy saving
features to the end users