SOP FOR PURCHASE OF CONSUMABLES


                Objective: To elaborate the procedure for purchasing consumable.

                Responsibility:
                      All the teaching/non-teaching staff members
                      Lab in-charges
                      Purchase Committee in charge
                      Heads of the Departments


                Procedure:


               Sl.      Activities                                  Responsibility          Target days

                         List of consumables required for
                         individual labs as per new revised                                 1 st  week of
               1.                                                   Lab in charges
                         curriculum is to be submitted by the                                April
                         Lab in-charges
                         The purchase committee in-charge            Purchase Committee
                         will scrutiny the requirements.             in- charge and Lab     2nd week of
               2.
                         Justifications have to be given for         in-                     April
                         the requirements if necessary.              charges
                         After the finalization of the
                         requirements, the individual lab-in
                         charges have to identify the reputed       Purchase Committee
               3.                                                   in- charge and Lab      3rd week of
                         suppliers (minimum of 3) and should
                         inform the same to the Purchase            in- charges              April
                         Committee in-charge
                         With the approval of the Purchase           Purchase Committee
                         Committee in-charge regarding the                                  3rd week of
               4.                                                    in- charge and Lab
                         suppliers, quotations have to be            in- charges             April
                         collected from those companies.
                         Based on the quoted price, the actual
                         cost for the entire requirements           Purchase
                         should be calculated with the              Committee in-            th
               5.        comparative statement by choosing          charge, HOD and         4   week of
                         the best supplier.  The approval of the    Principal                April
                         purchase for the actual amount has to
                         be received from the Management.