Page 74 - SOP Final
P. 74

SOP FOR PURCHASE OF EQUIPMENTS


                Objective: To elaborate the procedure for purchasing equipment

                Responsibility:
                     All the teaching/non-teaching staff members
                     Lab in-charges
                     Expert team
                     Purchase Committee in charge
                     Heads of the Departments

                Procedure:

                                                                                                 Target
               Sl. Activities                                           Responsibility
                                                                                                 days

                   List of equipment required for individual labs as                              st
               1.  per new revised curriculum is to be submitted by     Lab in charges           1  week of
                   the Lab in-charges                                                            Feb


                   An expertise team (set of Faculty members) within
                   the Department will scrutiny the requirements.       Expert team and          4th week of
               2.
                   Justifications have to be given for the              Lab in-charges           Feb
                   requirements if necessary.


                   After the finalization of the requirements, the
                   individual lab-in charges have to identify the       Expert team and          1st week of
               3.
                   reputed suppliers (minimum of 3) and should          Lab in-charges           March
                   inform the same to the expertise team.


                   With the approval of the expertise team regarding                             2nd week
               4.  the suppliers, quotations have to be collected from   Expert team and         of
                                                                         Lab in-charges
                   those companies.                                                               March


                   Based on the quoted price, the approximate
                   cost for the entire                                  Purchase
               5.  requirements should be calculated and the            Committee in-            4th week of
                                                                        charge, HOD and
                                                                                                  March
                   approval of the purchase for the approximate         Principal
                   amount has to be received from the Management.