                                                                                Proposal No. Q09526
                                                                                Date:  March 12, 2014

                                THIS PROPOSAL INCLUDED THE FOLLOWING PARTS AND SERVICES:

               One (1)      Direct Contact Water Heater System Including the Following:

                            1.      U. L. Listed Burner Assembly.
                            2.      Inlet and outlet connection for water.
                            3.      Inlet water distribution nozzle assembly.
                            4.      Flanged stack connection.  (12" diameter)
                            5.      Heat transfer medium.
                            6.      Dual walled water chamber.
                            7.      Top access and sidewall access manways on the heater shell.
                            8.      Type 304 stainless steel fabrication; other materials of construction are
                                    available if the supply water chemistry is of poor quality.

               One (1)      Stainless Steel Exhaust Stack:

                            1.      Ten (10) feet of stainless steel exhaust stack.  (12" diameter)

               One (1)      Gas Firing and Control System Including:

                            1.      Heavy duty industrial burner.
                                    1.1    Stainless steel inner and outer blast tube, UV scanner tube and
                                           diffuser.
                                    1.2    Full modulation control system.

                            2.      Combustion air blower.
                                    2.1    Stainless steel blower wheel.
                                    2.2    3/4 Hp. motor.

                            3.      Combustion air pressure sensor switch.

                            4.      Prepiped and prewired FM gas train including:
                                    4.1    Main gas shutoff valve.
                                    4.2    Main gas pressure regulator.
                                    4.3    Main gas valve, motorized with proof of closure.
                                    4.4.   Modulating butterfly valve.
                                    4.5    High gas pressure switch.
                                    4.6    Low gas pressure switch.
                                    4.7    Main gas test valve.