Page 22 - Cabrillo Square Closeout Manual
P. 22
EXHIBIT “A”
May 3, 2017
Total for Building #5: $27,554.12
Building #6:
o False Balcony:
• Unit #1053: (8)LF, Replacement.
• Unit #1055: (12)LF, Replacement.
• Unit #1045: (12)LF, Replacement.
• Unit #1047: (8)LF, Replacement.
o Unit handrails:
• Unit #2055: (11)LF, Good.
• Unit #2053: (14)LF, Replacement.
• Unit #1051: (28)LF, Good.
• Unit #1049: (28)LF, Replacement.
• Unit #2047: (14)LF, Repair.
• Unit #2045: (11)LF, Replacement.
• Unit #1047: (10)LF, Replacement.
• Unit #1053: (10)LF, Replacement.
Total for Building #6: 23,903.57
Building #7:
o False Balcony:
• Unit #1061: (6)LF, Removal..
• Unit #1057: (12)LF, Good.
• Unit #1059: (8)LF, Good.
o Unit handrails:
• Unit #1061: (28)LF, Repair.
• Unit #2059: (14)LF, Good.
• Unit #2057: (11)LF, Good.
Total for Building #7: $1,971.20
Building #8:
o False Balcony:
• Unit #2066: (11)LF, Repair.
o Unit handrails:
• Unit #2066: (7)LF, Replacement.
• Unit #2066: (16)LF, Repair.
• Unit #2066: (8)LF, Repair.
• Unit #2064: (14)LF, Repair.
• Unit #1062: (28)LF, Replacement.
Total for Building #8: $6,351.40
Page 4 of 9 Initial