Page 17 - Villas at Savona Close-out Manual
P. 17

off-site, do not permit economical bulk purchasing of materials within sixty (60) calendar days of the
                   date of initial material pricing, the ARCM shall be allowed recovery of documented material price
                   increases and/or additional material storage expenses during the course of construction.

               11.18  MAINTENANCE. At the completion of any construction Work, the ARCM will provide the
                   ASSOCIATION with a CLOSE OUT MANUAL.  The ASSOCIATION agrees that the ARCM is not
                   responsible for maintenance activities and that the ASSOCIATION will perform all recommended
                   inspections, maintenance and repairs as recommended in the CLOSE OUT MANUAL.

               11.19  ACCESS TO DOCUMENTS.  The ASSOCIATION shall provide the ARCM with access to all
                   existing litigation, arbitration, mediation, or other documents related to the Project defects pertinent to
                   this Agreement, and shall allow the ARCM to review such documents in the ARCM’S regional
                   office.  If the ASSOCIATION prefers that the ARCM make copies of necessary documents, the
                   ARCM shall do so as a reimbursable expense billable in addition to the Contract Amount.


                                 THE REST OF THIS PAGE IS LEFT BLANK INTENTIONALLY.






















































                                                          9 of 11
                 2015 JWC ARCM POST LIT                                              License ROC 190300 KB-1
   12   13   14   15   16   17   18   19   20   21   22