Page 22 - Villas at Savona Close-out Manual
P. 22
Exhibit "B"
Notes from Board Exec meeting with respect to repair priority
June 18, 2015
I. Geotechnical for Bldg 2-15 Common Areas
Task 1.0 a: Tight-line roof drains…. (Very Important)
Task 1.0 b: Rework grading…. (Very Important)
Task 1.0 c: Remove and replace selected worst case slabs (Very Important, with additional defi-
nition required)
II. Architectural
Task 3.0: Prep and Paint Buildings with Weatherproof Paint…. (Very Important)
Task 4.0: Windows…. (Very Important)
Task 5.0: Deck Surfaces (Important)
Task 6.0: Proactive Tune-up of Tile Roofs…. (Very Important, with results and options To Be Con-
sidered before determining scope)
Task 7.0: Proactive Inspection and Tune-up of Low Slope Roofs (Very Important, with results and
options To Be Considered before determining scope)
Task 8.0: Attic Gaps at Draftstops…. (Very Important)
Task 9.0: Interior Floors, Walls and Ceilings…. (Low Priority, consistent with the Board’s previous
determination that cosmetic interior repairs will be the responsibility of each condo owner. Interior
floors, walls and ceilings will repaired only in those worst case units in which extensive slab replace-
ments are necessary and widespread destruction warrants interior repairs.)
Task 10.0: Interior Doors…. (Low Priority, consistent with the Board’s previous determination
that cosmetic interior repairs will be the responsibility of each condo owner.)
Task 11.0: Tubs and Showers…. (Low Priority, consistent with the Board’s previous determina-
tion that cosmetic interior repairs will be the responsibility of each condo owner.)
Task 15.0: Recreation Area Repairs…. (To Be Considered)
III. Content Manipulation for Ground Floor Units Unlivable…. (Important, only as necessary. Not
anticipated by JWC.)