Proposal for Geotechnical Field Investigation Services
               Villas at Savona
               2.5   Project Meetings and Management

               It is estimated that one project meeting (via Conference call) will require the attendance of an
               Amec Foster Wheeler representative to discuss geotechnical considerations.



               3.0   FEES

               The geotechnical scope  of  work  defined  herein  will  be  performed for a  lump  sum  amount of
               $7,994.
               4.0   SCHEDULE

               The field layout will begin within 2 days after notice-to-proceed and provided all necessary access
               permits have been obtained. It is anticipated utility clearance and coordination will take 3 days.
               It is estimated that 1 day will be required to complete the field investigation.  Preliminary field data
               will  be  available immediately  following completion  of  the  field  investigation.    The final report
               (including  laboratory  testing) will  be  submitted  within 2 weeks after  completion  of  the  field
               investigation.

               If this proposal is satisfactory, please print and return a copy (via email or mail) of the attached
               Authorization to Proceed and return them to our office for execution.  An executed copy will then
               be returned to you for your records.


               Should you have any questions concerning this proposal, we would appreciate the opportunity to
               review and clarify.  We certainly appreciate your consideration of our firm for the geotechnical
               engineering services required for this project.

               Respectfully submitted,
               Amec Foster Wheeler
               Environment & Infrastructure, Inc.                 Reviewed by:








               Francisco J. Garza, PE                             Tony J. Freiman, PE
               Senior Geotechnical Engineer                       Associate Geotechnical Engineer

               Attachments: Services Agreement
               cc:     Addressee (PDF)
               G:\Geotechnical\2015 Proposals\PA15-11-04 Heerup_Villa at Savona\Proposal Heerup_Villas at Savona.docx















               955 E Knox Road
               Chandler, Arizona                      November 20, 2015                                Page 3