Page 11 - TRD
P. 11
Fig: Chittinad Cement Siding.
Energisation of By-pass line at MTMI:
Energisation of by-pass line OHE connecting mainline at KZJ end in BKL-MTMI
section to MTMI-JNPD branch line of 2.10 TKM done on 05.09.2021, after duly
obtaining the EIG sanction with EIG sanction no. 2106007, dated:03.06.2021
which will avoid the loco reversal at MTMI.
Fig: NI working at MTMI by-Pass
Electrification of new loading line at ZN yard:
New loading line of 117 Mts laid at ZN yard for easing the loading activities.
The electrification for new line with tramway OHE Done by TrD.
Fig : New line electrification work at ZN yard
Charging of New SSP at MTPI:
The electrification between PDPL-NZB commenced by RE organisation and
electrification up to MRTD was completed in the month of March-2021 in
phased manner. As a part of this work new SSP to be commissioned at
Metpally (MTPI) for sectioning purpose. Same was competed and charged on
30.06.2021 after duly completing the testing, attaining the EIG approval with