Electrification of 685 mts of new line at GDK siding:
As per the request from siding authorities for 685 mts of new line with
electrification for easing the loading activities at GDK siding, the works related
to TRD are completed.
Fig: GDK siding LOP
Provision of DJ STOP boards for 16 car MEMU @DKJ and SEM:
New 16 car MEMU services in place of 12 car MEMU are introduced between
BDCR-SRUR and SC-WD from 19/20.07.2021. New DJ Close boards are provided
at WD and KRA SSPs with suitable length for 16 car MEMU to avoid the bridging
of supply.
Fig: DJ Closed bords for 16 car MEMU.
Replacement of NICCO make contact wire:
NICCO make contact wire is a failure prone contact wire and replacement of
the same is the foremost work to do for TRD in the Division to avert the
breakdowns. Division has taken up the work and replacing in full pace from last
two years. There are Total 197 TLs identified for replacement. so far 37 TLs
(47387 Mts) of contact wire replaced.
Fig: Replacement of NICCO contact wire