Page 118 - Zero is Possible - Volume 3
P. 118

Mannersdorf
        World Class EI

        Locking down safety:

        Our centralized EI hub                                                                               AUSTRIA  Cement


        Opportunity             Results
        Ensure safe and efficient   •  Complex energy isolation
        complex isolations       process is ready for easy
        during shutdowns and     isolation of plant sections
        maintenance days.       •  Isolation gear and
                                 procedures at hand
        Solution                 save time and prevent
        Ready-to-go portable     shortcuts
        LOTOTO boxes for        •  Efficient coordination
        complex isolation        with control room and
        including all required gear,   Shift Supervisor                                                 Haimo Primas
        labeled equipment locks   •  Labeled equipment locks                                                CEO
        and specific LOTOTO      minimize errors
        procedures.
        Cost: 2 kCHF
        Timeline: 2 month




                                                                                                       Dejan Damljanovic
                                                                                                         Head of HSE