Page 118 - Zero is Possible - Volume 3
P. 118
Mannersdorf
World Class EI
Locking down safety:
Our centralized EI hub AUSTRIA Cement
Opportunity Results
Ensure safe and efficient • Complex energy isolation
complex isolations process is ready for easy
during shutdowns and isolation of plant sections
maintenance days. • Isolation gear and
procedures at hand
Solution save time and prevent
Ready-to-go portable shortcuts
LOTOTO boxes for • Efficient coordination
complex isolation with control room and
including all required gear, Shift Supervisor Haimo Primas
labeled equipment locks • Labeled equipment locks CEO
and specific LOTOTO minimize errors
procedures.
Cost: 2 kCHF
Timeline: 2 month
Dejan Damljanovic
Head of HSE