World Class EI
GREECE Cement Cut the walk, keep the lock
Opportunity
Results
• No waste of time to go from
Plant's extensive footprint
far from the control room
the work area to the control
room
required long walks to
coordinate Isolation Permits • Eliminate temptations to
and try-outs with the control bypass the process
room. • Reduced worker's fatigue
and increased productivity
Solution
Installation of 6 Energy
Isolation work stations with
access to the central control
Dimitrios Chanis system enabling coordination
CEO of work permits and try-outs
with the control room.
Cost: 25 kCHF
Timeline: 3 months