MOROCCO  Cement  All Cement Plants
                           Energy

                           100% renewable:

                           it’s possible



                           Opportunity
                                                      power all the cement sites
                           LafargeHolcim Morocco      in September 2024 to fully
                           is ambitiously working     with green energy, advancing
                           towards achieving 100%     towards the 100% target
                           decarbonized electrical
                           energy by 2025. This      Results
                           initiative aims to explore and   •  Achieved a 96%
                           implement the use of new   substitution rate with new
                           green renewable energy.    PPAs for Very High Voltage
                                                      (VHV) and High Voltage
     José Antonio Primo
          CEO              Solution                   (HV) plants by May 2024
                           •  Strategic Planning:    •  Saved 3.7 MCHF and
                            Incorporated into the LH   reduced emissions by
                            Morocco ARDI HAYATI       402 ktCO2 compared to
                            flagship project for      traditional power sources
                            meticulous execution      (2023 data)
                           •  Asset Efficiency: Optimized
                            the operation of the
                            Tétouan wind farm
                           •  Green Energy Contracts:
     Mohammed Al Fakihi
       Head of HSE          Secured long-term Power
                            Purchase Agreements (PPAs)