Page 137 - CRS E-booklet 2022
P. 137

135




                    Energisation of 4&5 of RKP-II siding at MCI station (TKM: 4.72, RKM: 2.555 KM):
                    Energisation of newly lied OHE on Road 4&5 of RKP-II siding at MCI station from OHE
                    mast  Loc.  No.  RKP  II/4/1001A  (Km.Ch.04/29.70)  to  Loc.  No.RKP  II/6/18
                    (Km.Ch.06/585.0) done on 27.08.2022 after duly obtaining the EIG vide sanction no.
                    2208025, dated: 22.08.22 and trail run conducted.
















                                       Fig: Charging of 4 & 5 Lines of RKP-II Sdg at MCI

              Energisation of newly electrified BG line between KHNAPUR(Excl.)-LATUR (Incl.)
               ROAD in VKB-PRLI section (RKM: 98.57, TKM: 112.60 KM):

               As a part of electrification works of single Broad Gauge(BG) line between Vikarabad
               (VKB)  –  Parli  Vaijnath(PRLI)  of  TKM:  313.86  (269  RKM),  the  section  between
               Khanapur(KHNP), Latur Road(LTRR) of TKM 113 (98.6 RKM) has been commissioned on
               29.09.2022  after  duly  obtaining  the  EIG  sanction  vide  statutory  authorisation  number
               2209035.  With  this  236.25  TKM  (RKM:  203.81)  of  electrification  has  been  completed
               between VKB-PRLI.
















               Fig: Speed trial commencement LTRR-KHNP         Fig: Inspection of chamfer & hole in neutral axis

                Energisation of Patch tripling works between CHERUV MADHAVARAM(CVV)-
                  KONDAPLLI (KI) in KZJ-BZA section (TKM: 5.52, RKM: 5.52 KM):
                    As a part of patch tripling works between KI-BPQ, the section between CVV-
                    KI  of  5.52  TKM/RKM  III   line  (U/D)  has  been  energized  on  20.09.2022,  after
                                             rd
                    duly  obtaining  the  EIG  sanction  vide  sanction  number  2208027,
                    Dated:16.08.2022 & statutory CRS and EIGoI inspection.

















                       Inspection of Neutral section @loc. 565/22    Insp.& Measurement of ATD parameters
   132   133   134   135   136   137   138   139   140   141   142