4.6.  MABD FOB (FULL FOB LAUNCHING IN 90 MIN BLOCK ONLY)
                   The  bed  plates  are  prefixed   and  welded  to   girders  taking  exact  site
                   measurements   from  centre  of  girders  to  respective  columns  centres   on
                   either  sides  of  platform  separately   and  accordingly  holes  are  drilled  in
                   cap  plate  and  bed  plates  instead  of  pre  assumption  of  all  columns   on
                   either  sides  of  the  platform  are  equidistant.By  doing  so  all  field  mistakes
                   during  errection  of  main  columns  have  taken  in  to  consideration  by
                   actually measuring and plumbing at site. So by doing above nearly 10 to
                   15 minutes have been saved for   matching of bed plates and cap plate
                   centres  and  doing  welding   and  redrilling  or  relocating  of  earlier  drilled
                   holes  for  each  girder  during  block.And  with  the  above  technique  the
                   holes for top bracings and cross frames are altered as per site conditions
                   for each girder instead of adopting same distances for all girders.With all
                   above  minute  planning   have  saved  for  3  girders  launching  3x15-45
                   minutes or else  it could have been required 2hours 30minutes block, but
                   work has been done  90mintues all 3 girders launching  by saving precious
                   45minutes block of both UP and DN lines.