Page 391 - GM E-BOOKLET 2022
P. 391
grade locations that is 258.300 to 259.250
nearly 1 km falling gradient and 259.252 to
259.400 level Gradient and again 259.400 to
259.500 raising gradient of 1 in 200. Due to
this change of grades this area has become
heavy water catchment area and always
water lagging at this bridge. As this bridge
is purely water way Bridge which is for
free flow of drainage/ rainwater only.
Permission for public use cannot be given
as per the guideline in vogue.
8 Shri. Soyam Bapu Sirpur 09.03.202 Construction of ROB in Adilabad 1. Drainage feasibility not available for 18.03.2
K
Rao member of the 1 town and RUB at RUB. 021
hazn
ag
Bharatiya Janata agar Sanjevayya colony at Sirpur 2. Existing ROB available to cross the
Party (LS) Kaghaznagar Railway track at this location.
3. Railway Boundary is less than 20mtrs at
above location.
389
4. So many points and crossing are
available.
5. Existing side drains available parallel to
track in UP line side.
6. SPM and Railway drinking water pipe
line available parallel to track in UP line
side.
9 Shri. Arvind Kortla Nil VI. RUB/ROB 6. Remarks: 02.11.2
Dharmapuri Railway As per Railway Board guidelines, no new 022
Hon’ble MP (LS) station 7. Construction of Railway Gate manned level crossing to be introduced on
Parliamentary at Rajaram )V) on Jagityal running Railway line. Therefore
Nizamabad-Reg. Metpally Bypass Road. If Gate is not construction of new Railway gate is not
Railwy possible, RUB may be possible. However, if State Government
station planed. comes forward or construction of
ROB/RUB on deposit terms, work will be
VII.StationPassenger Amenities taken up.