Page 79 - GM E-BOOKLET 2022
P. 79

3.1.4. INCREASE OF GOODS LOADED TRAIN:

                     Speed has been enhanced from 30kmph to 60kmph for goods loaded
                     trains  after  completing  TRR(P)  of  48KMs  between  KRMR-LPJL  stations
                     during the year.

              3.1.5. OPENING OF 3RD LINE :

                     During  the  year  2022-23,  3rd  line  between  MAGH-WIRR  for  a  length  of
                     17.93  KMs  &  BGSF-OPL  for  a  length  of  18.33km  has  been  opened  to
                     traffic.

              3.1.6. COMMSIONING OF NEW LINE:

                     New section was commissioned between Badrachalam & Sattupalli on
                     25.05.2022.

              3.1.7. GOODS SIDING:
                     Commissioning of goods sidings in MAGH & STBD was done in SC division.

                     For loading commodities, goods shed including railway line, loading PF
                     and 2km approach road was constructed in 20 days in MAGH. Division
                     has  achieved  a  milestone  by  commissioning  GCT  (Gati  Shakti  Multi-
                     modal Cargo Terminal) of M/s Rani and others at STBD which will add 10
                     rakes per month loading for Sc division. We can expect 3 rakes of iron
                     ore per day in MAGH which can generate Rs 61 lakh per rake earning
                     with total expected annual earning of Rs 500 Cr.












                                                             MAGH












                                                             STBD

                                                           77