3.1.13. REPAIRS TO PIT LINE NO 3 :

                     Improvements to pit line no 3 at the lower yard of SC station have been
                     done for 600 meters which was in very bad and unsafe condition. Work
                     was completed in a block of 40 days which involves drilling of 7500 no’s
                     of holes, fixing of 1830 no’s of new bearing plates and reconcreting of
                     entire surface.















           3.1.14. REPAIRS TO PIPES:
                       Hydrant piles and water pipes repairs have been done at DKJ, BDCR
                       stations.