3.2.3. PROVISION OF NEW FOBs:

                      16 Nos of new FOBs constructed till Oct’22 in SC division.













                                                         SC at KZJ end

               3.2.4. WIND ANEMOMETER:

                       As  per Para  No.717  of  IRBM,  where  high  winds  are  experienced  and
                       there  is  a  danger  of  vehicle  capsizing,  anemometers  should  be
                       installed at one of the railway station close to the bridge and suitable
                       working  rules  should  be  framed  prescribing  for  each  location  the
                       maximum  permissible  wind  velocity.  The  limiting  wind  velocity  will  be

                       specified by the Chief Engineer which should not exceed 72 Kmph. It
                       should  be  enjoined  that  the  Station  Master  should  control/stop  the
                       traffic on the section concerned when the wind velocity exceeds the
                       limits. He should also inform the Station Master on the other side and
                       the section controller of the need to control the traffic. In selecting the
                       bridges, the previous experience and the occurrence of the accidents
                       should be the guiding factor. Anemometers are installed at MAGH &
                       MCI sections.