               3.2.  BRIDGE


               3.2.1. DESTRESSED GIRDER BRIDGE:
                       Destressed  Girder  Bridge  no  71  of  1*12.00m  span  was  rebuilt  by
                       providing two spans of 4.275*6m (insitu) by removing girder and track
                       linking is done.














               3.2.2.  RELEASE  OF  STREEES  IN  ELASTOMERIC  BEARINGS  OF  PSC
                        GIRDERS:

                       During  installation  of  elastomeric  bearings,  they  got  distorted  due  to
                       external  stresses.  The  same  needs  to  be  relieved  for  the  better
                       performancve  of  girder.  And  the  same  is  done  at  br  no  77  by  lifting
                       girder using jacks at mean temperature.