5.  Penolakan dari masyarakat dan LSM sekitar lokasi   5.  Rejection from the community and NGOs around
                  proyek                                         the project site

               Sampai dengan Triwulan IV tahun 2019, secara   Until the fourth Quarter of 2019, in general, new
               umum proyek investasi baru masih dalam proses   investment projects were still being processed
               sesuai  dengan  jadwal  dalam  timeline.  Namun   according to the timeline schedule. However, there
               demikian, masih ada beberapa proyek lama yang   are still some old projects that have been planned but
               sudah direncanakan namun belum selesai, dimana   not yet completed, where the projects are a strategic
               proyek-proyek tersebut merupakan program       program of the company that can have an impact on
               strategis perusahaan yang dapat berdampak pada   system reliability and customer service, including:
               kehandalan sistem serta pelayanan pelanggan, di
               antaranya adalah:
               1.  Pembangunan Transmisi Batu Besar – Nongsa  1.  Development of the Big Stone Transmission -
                  Untuk progress Pembangunan Transmisi Batu      Nongsa For the progress of the construction of
                  Besar – Nongsa s.d Desember 2019:              the Great Stone Transmission - Nongsa until
                                                                 December 2019:
                  a.  Jumlah Tower Pembangunan Transmisi Batu    a.  The number of Batu Besar Transmission Tower
                     Besar – Nongsa yang akan dibangun sebanyak     Construction - Nongsa that will be built is 46
                     46 Tower                                       Towers
                  b.  Tower 24 – Tower 46, pondasi dan towernya   b.  Tower 24 - Tower 46, the foundation and tower
                     sudah selesai dibangun                         have been completed
                  c.  Telah dimulai pekerjaan yaitu pengukuran   c.  Work has begun to re-measure and install
                     ulang dan pemasangan patok sekitar Tower       pegs around Tower 2 to Tower 7, because the
                     2 s/d Tower 7 , karena lokasi tower digeser    location of the tower has been moved around
                     sekitar 20 meteran sehingga sebagian warga     20 meters so that some residents have no
                     sudah tidak ada penolakan lagi.                objections anymore.
                  d.  Hasil pengukuran ulang akan dituangkan     d.  The re-measurement results will be stated
                     dalam Design Map Tower Baru dan akan           in the New Tower Design Map and will be
                     dilakukan approval oleh PLN Batam (Divisi      approved by PLN Batam (Project Division)
                     Project)

               2.  Pembangunan PLTGU Tanjung Uncang kapasitas   2.  Development of Tanjung Uncang PLTGU with a
                  100 - 200MW Proyek pembangunan PLTGU ini       capacity of 100 - 200MW This PLTGU construction
                  menunjang untuk penambahan aset pembangkit     project supports the addition of PT PLN Batam’s
                  PT PLN Batam, sampai dengan Triwulan IV tahun   generating assets, until the Quarter of 2019 the
                  2019 progres fisik sudah mencapai 100%.        physical progress has reached 100% (shareholder
                                                                 loan funding source).

                  Dengan demikian, maka dapat disimpulkan        Thus, it can be concluded that the level of risk of
                  bahwa level risiko Proyek Investasi yang       the planned Investment Project cannot be realized
                  direncanakan tidak dapat direalisasikan yang   which was initially targeted to be at the final level
                  awalnya ditargetkan berada pada level akhir B3   B3 - Moderate, in Quarter IV of 2019 it has not
                  – Moderat, pada Triwulan IV tahun 2019 belum   been well mitigated, so it was concluded that this
                  termitigasi dengan baik, sehingga disimpulkan   risk level remained C3 - High with Low possibility
                  bahwa level risiko ini tetap C3 – Tinggi dengan   and Medium impact.
                  kemungkingan Kecil dan dampak Medium.

            11. Risiko Pelaksanaan K3 tidak Compliance Dengan   11.  Risk of OHS Implementation is not Compliance with
               Ketentuan (O.2.3)                              Provisions (O.2.3)

               Salah satu indikator penilaian dalam tingkat kesehatan   One of the assessment indicators in the level of
               perusahaan dan NKO adalah kepatuhan pada K3LH   company health and NKO is compliance with K3LH
               (Kesehatan, Keselamatan Kerja & Lingkungan Hidup)   (Health, Safety and Environment) which if it occurs
               yang jika terjadi dapat mengurangi sampai 10 poin.   can reduce up to 10 points. Therefore, this risk has
               Oleh karena itu, risiko ini berpotensi menggagalkan   the potential to frustrate the achievement of the AAA
               pencapaian sasaran Tingkat kesehatan perusahaan   (Healthy) and NKO> 95.00 corporate soundness
               AAA (Sehat) dan NKO>95,00 pada tahun 2019.     targets in 2019.

               Banyak sekali faktor yang dapat menyebabkan risiko
               ini, umumnya berasal dari kedisiplin individu dalam   There are so many factors that can cause this risk,
               menerapkan SOP K3 sampai dengan tersedianya    generally stemming from individual discipline in
               fasilitas Perlindungan & Pencegahan Kecelakaan yang   applying OSH SOP to the availability of adequate
               memadai. Oleh karena itu, para risk owner dengan   Accident Protection & Prevention facilities. Therefore,
               koordinasi dari departemen HSE telah melakukan   the risk owners in coordination  with the  HSE
               upaya-upaya rutin sebagai bentuk pencegahan mulai   department have made routine efforts as a form of
               dari penyediaan fasilitas Perlindungan & Pencegahan   prevention ranging from providing adequate Accident
               Kecelakaan yang memadai, sampai usaha-usaha    Protection & Prevention facilities, to efforts to improve
               untuk meningkatkan kedisiplinan petugas dalam   employee discipline in the form of outreach, simulation